SPV-190: We have a client with an identified system below 25 kW under an SPV contract. The client has to move from his current home and wants to move the system to the new home. Can this be accommodated under the terms of the SPV contract?

A Seller may request to replace a winning system identified in its SPV Contract prior to the system being energized. Such request must be made in writing to the IPA and is granted at the sole discretion of the IPA.  In addition, the substitute system must be within the great of + 25% or + 5 kW (whichever is greater) of the planned installed capacity of the system being replaced and must meet all the requirements for systems to be eligible for the SPV RFP. Please see section 3.10 of the SPV Contract for all requirements for substituting systems under the SPV Contract.