Archived-BEC-75: We have Bids for a Company that have been approved as winning Bids by the ICC. When will that Company send the partially executed supplier contract and related documents to us?

The timeline of the contract execution process for each Company is fully described in Paragraph VI.2.17 of the RFP Rules posted on March 16, 2022. For your convenience, we also provide it below:

“If the ICC approves some or all of a Bidder’s Bids for a procurement event for a Company, by 12 PM (noon) CPT on the first business day after the ICC decision, that Company prepares and sends a partially executed electronic copy of the applicable supplier contract and related documents to the Seller.”

A summary of the contract execution process was distributed to Sellers by email on May 18, 2022 with the subject line “Supplemental RFP – REMINDER: Contract Execution Process”.