IFP-99: We have contracted with a manufacturer of high efficiency solar panels. The manufacturer claims that the panels for our Project only need 1 acre per MW. Is there an opportunity to provide the information regarding those panels to the Procurement Administrator for the purposes of relaxing the site control requirements?

No.  At this time, all participants in the New Solar RFP must abide by the requirements of the RFP Rules, including showing site control for an area equal to 4 times the size of the Project (AC rating).