IFP-79: We participated in the first procurement event under the New Solar RFP and provided bid assurance collateral for our Projects. Do we need to post additional bid assurance collateral or amend the bid assurance collateral in any way if we participate in the second procurement event with the same Projects?

No. Bid assurance collateral that is tendered for the first procurement event and that is still required for the second procurement event will roll over to the second procurement event.   In that manner, a Bidder that provides bid assurance collateral in the first procurement event and that participates in the second procurement event with the same Projects will already have the bid assurance collateral in place for the second procurement event.