DG-140: What is the total capacity procured in the Fall 2017 DG RFP?

The Overall Target for the Fall 2017 DG RFP is 8,153 RECs. This represents approximately 5.5 MW using the capacity factor for solar photovoltaic cells and panels (fixed mount), of which approximately 4.4 MW is for ComEd’s portfolio, and the rest for AIC’s . However, the actual capacity procured may differ from these figures as the Targets can be met by procuring RECs from various resources, with varying capacity factors.