Bid assurance collateral in the form of cash or of a letter of credit to each of AIC, ComEd, and MEC is due with the Part 2 Proposal by 12PM (noon) CPT on August 23, 2017. In regards to the Supplier Fee, which is due after the Commission decision, the Procurement Administrator will inform Bidders of the amount required on a per REC basis no later than 6 PM two (2) business days before the Bid Date on August 31, 2017.
The calendar with all of the deadlines for the 2017 Wind and Solar RFP is available on the calendar page of the procurement website here: