Announcements


BEC-8: When should Bidders in the Fall 2019 BEC RFP start preparing their Letter(s) of Credit for submission?

The final versions of the Standard Pre-Bid Letters of Credit for each Company were posted on June 26, 2019 to the Final Materials page of the RFP Website. Bidders may begin working with their financial institutions at any time and are encouraged to begin as soon as practicable.

The Pre-Bid Letter(s) of Credit for Energy Products are due by 12 PM (noon) on Wednesday, August 28, 2019. The Pre-Bid Letter of Credit for the AIC Capacity Products is due by 12 PM (noon) on Tuesday, September 3, 2019.