Announcements


BEC-20: Where can I find redlines between the final supplier contracts between the Spring 2018 and Fall 2018 procurement events?

On June 20, 2018, the Procurement Administrator posted redlines between the final supplier contracts between the Spring 2018 and Fall 2018 procurement events. Redlines reflect differences between the final document posted on March 13, 2018 for the Spring 2018 BEC RFP and the final document posted on June 20, 2018 for the Fall 2018 BEC RFP. These documents are available on the Final Materials page of the Fall Block Energy and Capacity section of the RFP website.