STP-32: Which Inserts will need to be re-submitted in the event that the Officer of the Bidder named in the Part 1 Form will not be available on April 6 to execute the contracts?

If the Officer of the Bidder is available to complete the certifications in the Part 2 Proposal, nothing needs to be resubmitted. If the Officer of the Bidder will not be available only when needed to sign the applicable supplier contract and related documents, the Bidder will advise the Company of this fact, will name another individual to sign the applicable supplier contract and related documents, and will confirm that this individual is an officer, a director, or an individual otherwise authorized to undertake contracts (including the applicable supplier contract documents) and bind the Bidder. Please see Paragraph VI.2.15 of the RFP Rules.

This response assumes that the Officer of the Bidder is available to sign the certifications of the Part 2 Proposal. If this assumption is incorrect please submit a follow-up question.