SPV-193: Will there be a further procurement event under the Supplemental Photovoltaic Procurement Plan? What are other renewable energy procurements are planned thus far for 2017?

The Supplemental Photovoltaic Procurement Plan developed by the IPA and approved by the Illinois Commerce Commission allows for a possible fourth procurement event in Spring 2017, called the Supplemental Photovoltaic Contingency Procurement. The Agency has determined that it is not necessary to conduct a Supplemental Photovoltaic Contingency Procurement.

The following renewable energy procurement events for 2017 are planned and tentative schedules have been released:

  • Two procurements for distributed renewable generation resources on behalf of Ameren Illinois, ComEd, and MidAmerican pursuant to the Agency’s 2017 Procurement Plan. The first of these procurement events is planned for this Spring and the schedule is available here:

   https://www.ipa-energyrfp.com/calendar/

  • Once Public Act 99-0906 becomes effective on June 1, 2017, the IPA expects to conduct an initial forward procurement event for Wind/Solar in summer 2017. The expected schedule, which is provided here:

   https://www.illinois.gov/sites/ipa/Documents/2017-Schedule-Announcement.pdf

   has bidder registration beginning June 22, 2017 and a Bid Date of August 10, 2017.

Additional forward solar procurement events will be scheduled at a later date. All such schedules will be posted to the Calendar page of the procurement website.

If you have not already done so, we suggest that you complete the form to Register to receive updates and information regarding the RFPs. These updates will include announcements of upcoming procurement events.