STP-15: Will we be considered previously qualified and eligible for the abbreviated Part 1 Proposal process if our sister company has participated in the Standard Products RFP in 2015?

No. A Bidder that successfully completed the Part 1 Proposal for a 2015 procurement event under the Standard Products RFP is said to have “previously qualified”. Such a Bidder is generally eligible to participate in an abbreviated process to submit the Part 1 Proposal (provided there has been no change in the Bidder’s corporate structure). Conversely, if an entity did not complete the Part 1 Proposal for a 2015 procurement event under the Standard Products RFP, that entity is not eligible to participate in an abbreviated process.