STP-57: Would it be permissible for an individual other than the Officer of the Bidder designated in the Part 1 Application to sign the supplier contract?

According to paragraph VI.2.16. of the Fall 2015 RFP Rules posted to the Standard Products Section of the website, it is expected that the Officer of the Bidder will sign a copy of the partially executed applicable supplier contract and related documents. If the Officer of the Bidder is not available to sign the applicable supplier contract and related documents, the Bidder will advise the Company of this fact, will name another individual to sign the applicable supplier contract and related documents, and will confirm that this individual is an officer, a director, or an individual otherwise authorized to undertake contracts (including the applicable supplier contract documents) and bind the Bidder.