The RFP Rules anticipate the Bidders may need more to time to provide certain information. For new systems, the RFP Rules provide a delay up to the Part 2 Date (October 1) to provide the following information:
- Host name and contact information, and acknowledgment from Host if the owner of the system is not also the host;
- Interconnecting distribution company to which the system is connected;
- Customer account number;
- Tracking system from which RECs will be transferred; and
- Bidder-Owner agreement if the Bidder is not the Owner (a contract or letter of intent).
For existing systems, the RFP Rules provide a delay up to the Part 2 Date (October 1) to provide the following information:
- Documentation showing the system energized date; and
- Bidder-Owner agreement if the Bidder is not the Owner (a contract or letter of intent).