BEC-50: We want to start preparing our Part 1 Proposal as soon as possible. Is it possible for the Procurement Administrator to post draft of the Inserts and other documents related to the Part 1 Proposal on the Draft Documents page of the Spring Block Energy and Capacity tab of the procurement website?

The Inserts to the Part 1 and Part 2 Forms will not be provided in draft form as only the final versions would be accepted for submission with your Proposal. On the calendar for these procurement events, the Final RFP Documents, including the Inserts, are scheduled to be posted to the Final Materials page of … Continue reading We want to start preparing our Part 1 Proposal as soon as possible. Is it possible for the Procurement Administrator to post draft of the Inserts and other documents related to the Part 1 Proposal on the Draft Documents page of the Spring Block Energy and Capacity tab of the procurement website?

BEC-48: Why was only a portion of the ZRC Target filled in the Spring 2018 procurement event?

The evaluation of Bids for the procurement of the Capacity Product for AIC proceeds in two steps.  In the first step, all Bids that fail to meet the benchmarks are eliminated.  In the second step, the Procurement Administrator evaluates the Bids that meet or beat the benchmarks and selects the lowest priced Bids.  The outcome … Continue reading Why was only a portion of the ZRC Target filled in the Spring 2018 procurement event?

BEC-42: The Officer of the Bidder who made the representations and certifications required by the Part 1 Proposal is unavailable and cannot make the representations and certifications required by the Part 2 Proposal. How should we proceed?

All representations and certifications required by the Block Energy and Capacity RFP, including those in the Part 1 Proposal and the Part 2 Proposal, must be made by a single individual who is an Officer of the Bidder. An Officer of the Bidder is an individual empowered to undertake contracts and bind the Bidder. Please … Continue reading The Officer of the Bidder who made the representations and certifications required by the Part 1 Proposal is unavailable and cannot make the representations and certifications required by the Part 2 Proposal. How should we proceed?