BEC-2: When will the schedule for the Spring 2024 Block Energy and Capacity RFP be available?

On September 25, 2023, the IPA filed its 2024 Electricity Procurement Plan (“2024 Plan”) to the Illinois Commerce Commission (“ICC”). The ICC issued its Order with regards to the Plan on December 14, 2023. The Plan approved by the ICC provides for an energy procurement event and a capacity procurement event for Spring 2024. The … Continue reading When will the schedule for the Spring 2024 Block Energy and Capacity RFP be available?

BEC-1: Are solar projects eligible to participate in the BEC RFP?

Under the supplier contract, there is no generation source specified for purposes of meeting the obligations. A Product in the procurement of Capacity is an annual Zonal Resource Credit, as such term is defined in MISO’s Business Practice Manuals and MISO’s Open Access Transmission, Energy and Operating Reserve Market Tariff. A Product in the procurement … Continue reading Are solar projects eligible to participate in the BEC RFP?