2017 Utility DG Procurement Events (AIC, ComEd, and MEC)
On September 27, 2016, the IPA submitted its Procurement Plan (“Plan”) to the Illinois Commerce Commission (“ICC”) in compliance with Public Act 095-0481 (the “Act”), which includes the Illinois Power Agency Act (“IPA Act”). The ICC issued its Order with regards to the Plan on December 13, 2016. The Plan approved by the ICC provided for two (2) procurements, one in the Spring and one in the Fall, of Renewable Energy Credits (“RECs”) from distributed generation (“DG”) resources using the already collected funds from Alternative Compliance Payments for AIC and ComEd and using the renewable resources budget for MEC.
Fall 2017 DG Calendar (June 23, 2017, revised September 08, 2017)
Spring 2017 DG RFP Calendar (April 12, 2017)
Announcements – Spring and Fall 2017 DG RFPs
Click here to view Utility DG FAQs.
Fall 2017 DG RFP Results
- Fall 2017 DG Results (October 19, 2017)
- ICC Public Notice of Fall 2017 DG Results (October 19, 2017)
Spring 2017 Distributed Generation RFP Results
- DG RFP Results Spring 2017 (May 03, 2017)
- ICC Public Notice of Spring 2017 DG Results (May 03, 2017)
You may register to receive announcements for the procurement events under the Spring Utility DG RFP or “DG RFP” through the Register Page by selecting the “Utility DG” option.
Fall 2017 Utility DG
FINAL Fall 2017 DG Bidder Information Webcast
- Fall 2017 DG Bidder Information Webcast Presentation (September 8, 2017)
- Fall 2017 DG Bidder Information Webcast Recording (September 08, 2017)
FINAL Fall 2017 Distributed Generation RFP Documents
- DG RFP Rules (September 08, 2017)
- Appendix 1: (AIC) DG Renewable Energy Credit Agreement (see below)
- Appendix 2: ComEd Master DG REC Purchase and Sale Agreement (see below)
- Appendix 3: RESERVED
- Appendix 4: Part 1 Form (Illustrative) (September 07, 2017)
- Appendix 5: Sample Documents (August 15, 2017)
- Appendix 6: Part 2 Form (Illustrative) (September 08, 2017)
- Appendix 7: Trial Bid Form (September 08, 2017)
- Appendix 8: Evaluation Process (September 08, 2017)
- Appendix 9: Standard IPA Letter of Credit (August 15, 2017)
- Appendix 10: Confidentiality Statement (September 08, 2017)
FINAL Fall 2017 AIC DG Renewable Energy Credit Agreement
FINAL Fall 2017 ComEd Master DG REC Purchase and Sale Agreement
Information Release
Invitation to Comment
DRAFT DG REC Contracts
- AIC DG Renewable Energy Credit Agreement (August 08, 2017)
- ComEd Master DG REC Purchase and Sale Agreement (without Coversheet) (August 08, 2017)
- Coversheet of Master DG REC Purchase and Sale Agreement (with amendments to the Master DG REC Purchase and Sale Agreement) (August 08, 2017)
- Redlines
Early Information Release
- Early Information Release (July 28, 2017)
- Sample Documents (July 28, 2017)
- Standard IPA Letter of Credit (July 28, 2017)
Spring 2017 Utility DG
Spring 2017 Distributed Generation Bidder Information Webcast
- IPA DG Bidder Information Webcast Presentation (March 27, 2017)
- IPA DG Bidder Information Webcast Recording (March 27, 2017)
FINAL Spring 2017 Distributed Generation RFP Documents
- DG RFP Rules (March 27, 2017)
- Appendix 1: (AIC) DG Renewable Energy Credit Agreement (see below)
- Appendix 2: ComEd Master DG REC Purchase and Sale Agreement (see below)
- Appendix 3: (MEC) DG Renewable Energy Credit Agreement (see below)
- Appendix 4: Part 1 Form (Illustrative) (March 27, 2017)
- Appendix 5: Sample Documents (March 27, 2017)
- Appendix 6: Part 2 Form (Illustrative) (March 27, 2017)
- Appendix 7: Trial Bid Form (March 27, 2017)
- Appendix 8: Evaluation Process (March 27, 2017)
- Appendix 9: Standard IPA Letter of Credit (March 27, 2017)
- Appendix 10: Confidentiality Statement (March 27, 2017)
FINAL Spring 2017 (AIC) DG Renewable Energy Credit Agreement
- Final (AIC) DG Renewable Energy Credit Agreement
- Redline Comparisons
FINAL Spring 2017 ComEd Master DG REC Purchase and Sale Agreement
- Final ComEd Master DG REC Purchase and Sale Agreement
- Redline Comparisons
FINAL Spring 2017 (MEC) DG Renewable Energy Credit Agreement
- Final (MEC) DG Renewable Energy Credit Agreement
- Redline Comparisons
Early Information Release
- Early Information Release (March 03, 2017)
- Sample Documents (March 03, 2017)
- Standard IPA Letter of Credit (March 03, 2017)
Spring 2017 Distributed Generation Comment Process
DRAFT Spring 2017 (AIC) DG Renewable Energy Credit Agreement
- Draft (AIC) DG Renewable Energy Credit Agreement
- Redline Comparisons
DRAFT Spring 2017 ComEd Master DG REC Purchase and Sale Agreement
- Draft ComEd Master DG REC Purchase and Sale Agreement
- Redline Comparisons
DRAFT Spring 2017 (MEC) DG Renewable Energy Credit Agreement
- Draft (MEC) DG Renewable Energy Credit Agreement
- Redline Comparisons
Utility DG FAQs
Click on the question to see the answer:
Will there be a further procurement event under the Supplemental Photovoltaic Procurement Plan? What are other renewable energy procurements are planned thus far for 2017?
The Supplemental Photovoltaic Procurement Plan developed by the IPA and approved by the Illinois Commerce Commission allows for a possible fourth procurement event in Spring 2017, called the Supplemental Photovoltaic Contingency Procurement. The Agency has determined that it is not necessary to conduct a Supplemental Photovoltaic Contingency Procurement.
The following renewable energy procurement events for 2017 are planned and tentative schedules have been released:
- Two procurements for distributed renewable generation resources on behalf of Ameren Illinois, ComEd, and MidAmerican pursuant to the Agency’s 2017 Procurement Plan. The first of these procurement events is planned for this Spring and the schedule is available here:
https://www.ipa-energyrfp.com/calendar/
- Once Public Act 99-0906 becomes effective on June 1, 2017, the IPA expects to conduct an initial forward procurement event for Wind/Solar in summer 2017. The expected schedule, which is provided here:
https://www.illinois.gov/sites/ipa/Documents/2017-Schedule-Announcement.pdf
has bidder registration beginning June 22, 2017 and a Bid Date of August 10, 2017.
Additional forward solar procurement events will be scheduled at a later date. All such schedules will be posted to the Calendar page of the procurement website.
If you have not already done so, we suggest that you complete the form to Register to receive updates and information regarding the RFPs. These updates will include announcements of upcoming procurement events.
Does the IPA certify behind-the-meter Distributed Generation solar facilities for generating and tracking Illinois SRECs?
Illinois does not have a state process for certification of renewable energy facilities.
Separately the IPA has developed standards for the metering requirements of renewable energy PV facilities that are bid in to the IPA’s procurement events. The standards are found here:
https://www.illinois.gov/sites/ipa/Documents/IPA-metering-accuracy-standard-5-14-15.pdf
For information on generating and tracking of RECs, please contact M-RETS or GATS:
M-RETS Registry
Contact: Bryan Gower, M-RETS Administrator
Email: mrets@apx.com
Phone: 408-899-3340
gatsadmin@pjm-eis.com
(877) 750-GATS (4287)
For additional information on procurement events planned for 2017, as well for the change in definition of distributed renewable energy generation device pursuant to Public Act 99-0906 (which becomes effective on June 1, 2017), please consult:
https://www.illinois.gov/sites/ipa/Pages/News.aspx
https://www.illinois.gov/sites/ipa/Pages/Renewable_Resources.aspx
Is it expected that both existing and new projects will be allowed to participate in the Utility DG RFP?
It is expected that the procurement events under the Utility DG RFP will allow participation from both new and existing systems (please consult the Utility DG RFP when it is release for full eligibility criteria).
We are an aggregator and we are asking that certain parameters of the upcoming Utility DG RFP be announced by February 28, namely the capacity factors to be used and the actual Supplier Fee. Is that feasible?
With respect to the Supplier Fee, the IPA’s 2017 Procurement Plan (https://www.illinois.gov/sites/ipa/Documents/2017ProcurementPlan/ICCFiling/2017%20IPA%20Procurement%20Plan%20for%20ICC%20Filing%20%28Final%209-27-16%29.pdf)
states that “an estimated Supplier Fee per REC will be announced prior to the opening of bidder registration, and the final Supplier Fee per REC will be announced after bidder registration is completed but prior to the bid due date.” Typically the estimated Supplier Fee is provided during the webcast held prior to the opening of bidder registration, scheduled for March 27. It is not feasible to provide an estimate of the Supplier Fee on February 28. In response to your request, we will endeavour to provide an estimated Supplier Fee by March 3. This estimate will be such that the actual Supplier Fee that will be announced once registration is completed but prior to the bid due date will be NO HIGHER than the previously announced estimated Supplier Fee.
With respect to the capacity factors, the final capacity factors were expected to be made available when the final RFP Rules are released, which is scheduled for March 27, 2017. It is not feasible to provide final capacity factors by February 28. Please take note of the capacity factors that were used in prior DG procurement events, available on p.6 of this document:
https://www.ipa-energyrfp.com/?wpfb_dl=901
In response to your request, we will endeavour to provide any updates to these capacity factors by March 3 as well. Such updates will provide to bidders the final capacity factors and these capacity factors will not be subject to further change when the final RFP Rules are released.
Can a distributed generation system interconnected at the distribution level of a municipal utility or a rural electric cooperative in Illinois eligible to be bid in the DG RFP?
Yes.
For the Utility DG RFP, one of the systems that I could include is one where the system will be built on a site owned by someone other than the owner of the system. Is such a system eligible for participation?
The “host” for a system is the individual or entity that owns or controls the site where the system will be installed. In the case you present, the host is a different individual or company from the owner of the system (the individual or company that will have title to the RECs produced by the system).
Systems for which the owner and the host are different individuals or companies are eligible for participation in the DG RFP. However, such systems are typically required to submit additional documentation in the form of a “Host Acknowledgment”. A Host Acknowledgment is a statement from the host that the host knows about the planned system and agrees to the system being installed. A sample of the Host Acknowledgment from a prior procurement event is provided here:
https://www.ipa-energyrfp.com/2016-renewable-energy-resources-section/
(click on Appendix 5 under Spring 2016 Distributed Generation FINAL RFP Documents).
What was the Supplier Fee for the Spring 2016 Utility DG RFP?
The Supplier Fee for the Spring 2016 Utility DG RFP was $11.25 per REC for the quantity of RECs associated with winning Bids across all Delivery Years.
The Supplier Fee is paid only by suppliers whose bids are approved by the Illinois Commerce Commission.
Can the system owner use a parent guaranty instead of a letter of credit under the terms of the DG RFP and applicable supplier contract?
The Bidder (the company that will be presenting a proposal under the Utility Distributed Generation Request for Proposal, the “DG RFP”) will be required to present a Letter of Credit to support its bids with the Illinois Power Agency (“IPA”) as beneficiary. The terms of this Letter of Credit have been released and are available here:
https://www.ipa-energyrfp.com/spring-utility-dg/final-materials/
Should the Bidder have Bids that are approved by the Illinois Commerce Commission, the Letter of Credit would still be held during the term of the supplier contract. Please see Section V.2.3. of the DG RFP Rules for information on the reduction and return of the Letter of Credit.
Please note that the Bidder and the system owner may or may not be the same person/company. The requirement to provide a Letter of Credit applies to the Bidder.
Regarding the System Identification Form (Exhibit B), would you please let me know if the Host Acknowledgement and Certification form (Appendix C) is required in the instance that the system owner is not the host?
You seem to be referring to documents appended to the contract forms that were used in the procurement events under the Supplemental Photovoltaic Procurement Plan (“SPV”). Please note that the procurement event under the Utility DG RFP to be held this Spring uses an entirely different contract form and the requirements for the submission of a Proposal will be different from the requirements in the SPV procurement events.
Please see the draft contract form here (comments are due March 9):
https://www.ipa-energyrfp.com/spring-utility-dg/
Please also note that, to assist bidders who may preparing to participate in the DG RFP, the Procurement Administrator has made an early release of information and documents, including a Sample Host Acknowledgment. This Host Acknowledgment is included in the “Sample Documents” posted to this page:
https://www.ipa-energyrfp.com/spring-utility-dg/final-materials/
While the DG RFP Rules have not been released, it is anticipated that the Host Acknowledgment will be required for a system presented as part of your Proposal if: (i) the system is new (i.e., energized on or after June 1, 2017); and (ii) the System Owner and the Host are different entities or individuals.
As an alternative to issuing a Letter of Credit, are bidders able to meet collateral requirements by posting an equivalent amount of cash to the IPA?
No, the IPA will not accept cash to meet collateral requirements for the Utility DG RFP. All bidders must submit a Letter of Credit with their Part 2 Proposal. This Letter of Credit stays in place at the start of the supply period to the extent that some of the systems presented in the Proposal have not begun accumulating metered deliveries or to the extent that some systems in the Small Size Class have not yet been identified.
All suppliers that are considering participation in the Utility DG RFP should begin at the earliest opportunity to work with their financial institutions to issue the Letter of Credit. The Letter of Credit has been posted here:
https://www.ipa-energyrfp.com/spring-utility-dg/final-materials/
If the financial institution of the bidder would like to propose modifications to the Letter of Credit, such modifications can be presented by the Bidder to the Procurement Administrator prior to the Part 1 Date (the date at which Part 1 Proposals are due).
Are the Utility DG procurement events targeted more to aggregators or individual system owners? Do the participants buy or sell renewable energy credits?
The IPA Utility DG procurement events are targeted more to aggregators (rather than individual system owners) to SELL (rather than buy) renewable energy credits.
Where can I find information for homeowners who may wish to participate in the IPA Utility DG procurement event through an aggregator? Is there a list of aggregators on your website?
The Illinois Solar Energy Association has information for homeowners generally and with respect to the IPA procurement events in particular:
http://www.illinoissolar.org/Procurement
The results of previous procurement events also provide the list of aggregators. These aggregators have been winning suppliers in the IPA’s procurement events:
https://www.ipa-energyrfp.com/?wpfb_dl=918
We are trying to become aggregators, but cannot find a process of how to do that. Can you give any guidance?
There is no certification or formalized process to become an aggregator. An aggregator refers to an entity that presents renewable energy systems that it does not own but for which it has ownership of RECs or the contractual right to legally transfer or assign the RECs to the utility.
Under the Utility DG RFP (“DG RGP”), the Bidder is expected to serve as the counterparty under the applicable supplier contract with the utility for the delivery of RECs. There is a minimum 1 MW bid. While the Bidder can be a system owner or an aggregator, if smaller systems are presented, it would be expected that the bidder is an aggregator.
In the presentation of the proposal, an aggregator must demonstrate that it has ownership or the contractual right to legally transfer or assign RECs through executed Letters of Intent for each system that it does not own.
Is there a limitation on how large bids may be (so long as they meet the 1 MW threshold), or how many bids one Bidder can submit?
While the RFP Rules have yet to be finalized, we expect that a first limitation will be that the Bidder can, for the Large Size Class (systems 25 kW or above), present systems that together produce an annual quantity of RECs up to and including the overall Target (across all three utilities). Similarly, for the Small Size Class (systems below 25 kW), we expect that the limitation will be that the Bidder can present systems and a forecast quantity that together produce an annual quantity of RECs up to and including the overall Target (across all three utilities).
A second limitation is that any Individual system presented as part of a proposal for the Spring Utility DG RFP (“DG RGP”) is limited in size to 2,000 MW nameplate capacity (DC rating).
A third limitation is that a Bidder can submit a single proposal in response to the DG RFP.
Can a 1 MW bid include systems from both the Small Size Class and the Large Size Class? Must the Bidder present a single blended bid price? Will there be a single blended price under the applicable supplier contract?
Components of the first 1 MW Block presented by a Bidder may be of different technologies, may be from different Size Classes, and, for the Small Size Class, may be from identified systems or may include a forecast quantity. To the extent that the first 1 MW Block features RECs from both the Large and the Small Size Classes, the Bidder must provide two Bid prices, a Bid price for each Size Class. Each price is a blend to the extent that the price applies potentially to several systems.
Under the applicable supplier contract with a given utility, there is a single blended price for each Size Class, which is calculated as the weighted average of the winning bid prices of the RECs that have been selected for award under the RFP process for that contract.
If we identify a system as part of our bid, but the system does not materialize and does not begin accumulating metered deliveries by May 31, 2018, can we substitute that system?
No. While the contracts for the Distributed Generation RFP (“DG RFP”) are not yet finalized, under the terms of the current draft contracts, there is no allowance for substitution (adding a system in place of a system identified as part of a winning bid). In the case that an identified system does not materialize or accumulate metered deliveries by May 31, 2018, the Bidder would forfeit the collateral associated with the RECs from such system. Furthermore, the project would be removed from the applicable supplier contract with a utility and the maximum quantity of RECs to be delivered under the contract would be reduced accordingly.
Is there a process to amend the system size under the terms of the draft DG supplier contracts?
No. Please review the DG contracts, which are on a portfolio basis and are not structured on a system by system basis. As part of the Proposal, a Bidder will be required to both identify the size of a system and to certify that the systems’ characteristics, including size, are true and accurate to the best of the Bidder’s knowledge and belief. The applicable supplier contract will specify a Maximum Annual Quantity to be delivered under the contract, which can be supplied from any of the systems identified as part of the bid (or identified subsequently if the winning bid initially specified a forecast quantity).
Can you clarify the deadlines to energize systems? Do systems identified in the bid have one year from bid date to install? Do systems from a forecast quantity have to be identified in 9 months from the bid date?
For the Spring Utility DG RFP, Bidders may include in their proposal both: 1) identified systems; or 2) a forecast quantity, a quantity of RECs that are not associated with identified systems in the Small Size Class. Identified systems must begin accumulating metered deliveries by the end of the 2017-18 year (on or prior to May 31, 2018).
For a forecast quantity, the Bidder must identify the systems no later than nine months after the start of the delivery year (i.e., by February 28, 2018) and such systems must begin accumulating metered deliveries by February 28, 2019.
Are the RFP Rules and final materials available for the DG RFP?
The RFP Rules and final materials are not yet available. These are scheduled to be posted to the Final Materials page of the Spring Utility DG section of the procurement website on March 27, 2017. Should draft documents become available, they will be posted to the Draft Documents page and an announcement will be sent to registrants and posted to the procurement website.
Please also note that, to assist bidders who may be preparing to participate in the DG RFP, the Procurement Administrator has made an early release of some information and documents, including a Sample Host Acknowledgment. This information is posted here:
https://www.ipa-energyrfp.com/spring-utility-dg/final-materials/
Do you have a sample of an acceptable "Letter of Intent"?
Samples of the Letter of Intent can be found in the document titled ‘Sample Documents (March 3, 2017)’ that is posted here: https://www.ipa-energyrfp.com/spring-utility-dg/final-materials/.
Will the IPA procure the lowest bids up to a specific REC quantify or a dollar amount?
Bids that meet or beat the benchmarks are selected in price order until the Target quantity of RECs is met on an annual basis or until the Budget is exhausted, whichever comes first.
Does a winning bidder receive their own bid price, or a market-clearing price?
A winning bidder receives the average of the bidder’s own winning bids (and not a market-clearing price).
When will the Supplier Fee be announced?
The Supplier Fee will be announced no later than the Part 2 Date. This Supplier Fee will not exceed $3.00/REC (the final Supplier Fee may be lower but will in no event be higher than $3.00/REC).
If we get an award for a forecast quantity of RECs for the Small Size Class under the Utility DG RFP, what are the consequences to us if we fail to identify the systems by the deadline or if the systems we do identify fail to accumulate metered deliveries by the deadline stated in the contract? If we get an award for systems not yet in operation (in either Size Class), what are the consequences to us if these systems fail to accumulate metered deliveries by the deadline?
The first consequence is that the quantities for which you can get paid under the contract will be reduced by the RECs associated with the systems that you fail to identify or by the RECs associated with the systems that fail to accumulate metered deliveries by the deadline. The second consequence is that the IPA will make a draw upon the letter of credit in an amount of $4 for each REC that was included in the winning Bids but that is deducted from the quantities for which you can get paid under the contract.
Is there collateral to be posted during the term of the DG contract? Where is this information in each of the applicable supplier contracts?
The amount of collateral to be posted is $4/REC based on the number of RECs across the term of the contract associated with your winning bids as specified in the 2017 Procurement Plan. This amount will be further explained in the RFP Rules when these become available. This amount of collateral is to be posted as a Letter of Credit with the IPA as beneficiary. The collateral is not posted with the utility as a term of the applicable supplier contract with the utility.
What are the circumstances in which I can lose all or part of the collateral that I would post during the term of the DG contract as a Letter of Credit with the IPA as beneficiary?
Please see the Letter of Credit here. The conditions for drawing on the letter of credit are provided in Paragraph 2 to the Letter of Credit.
Is it an event of default under the applicable supplier contract for a utility if we do not deliver up to the Maximum Annual Quantity each Delivery Year?
No, it is not an event of default under the applicable supplier contract for a utility if you do not deliver up to the Maximum Annual Quantity provided that you meet the following conditions. If you do not meet the Maximum Annual Quantity, you must provide all of the RECs from the systems associated with the applicable supplier contract with the utility; you must not be withholding RECs from the utility or selling RECs from such systems to another party.
If a system fails to be built or energized, is the penalty forfeiture of the Performance Assurance of $4/REC, or is the penalty that the Supplier Fee is retained by the IPA, or both?
A winning bidder will have seven (7) business days after the Illinois Commerce Commission’s approval of the procurement event to pay the supplier fee associated with the winning bids. The supplier fee is not returned or refundable.
With its Part 2 Proposal, a Bidder must provide a Letter of Credit in an amount of $4 times the number of RECs that the Bidder can win across all systems and any forecast quantity for the five (5) Delivery Years under the applicable supplier contracts. This Letter of Credit stays in place, reduced on a prorated basis based upon the winning Bids, at the start of the supply period to the extent that some of the systems presented in the Proposal have not begun accumulating metered deliveries or to the extent that some systems in the Small Size Class have not yet been identified.
In the case that a system fails to be built or energized, the Bidder would forfeit the collateral associated with the RECs from such system. Furthermore, the project would be removed from the applicable supplier contract with a utility and the maximum quantity of RECs to be delivered under the contract would be reduced accordingly.
If a system identified in our proposal fails to deliver the expected number of RECs, is there a penalty?
In the event that an identified system in your proposal delivers RECs under the contract, but is not able to deliver the intended number of RECs designated in the contract, there is no penalty.
When is the Letter of Credit due? If our bank has requests for alternate language in some instances or non-material modifications, is there a process to submit these to the Procurement Administrator?
A Bidder must submit an original executed Letter of Credit to support its bids with its Part 2 Proposal. The Part 2 Proposal, including the Letter of Credit, must be submitted by 12 PM (noon) Thursday, April 20, 2017.
The Letter of Credit is available in final form here: https://www.ipa-energyrfp.com/spring-utility-dg/final-materials/. Should your financial institution have requests for alternate language, you may submit comments on the Letter of Credit to the Procurement Administrator by the time Part 1 Proposals are due, which is 12 PM (noon) CPT on April 5, 2017.
Can you confirm that there is no draw against the Letter of Credit if a system associated with an applicable supplier contract with a utility under the DG RFP does not deliver the expected quantity? Is there a draw or another financial consequence if we fail to deliver the maximum annual quantity in a delivery year under the contract?
As long as the system has been registered with PJM GATS or M-RETS and the initial meter read date of such system occurs by the deadline in the applicable supplier contract with the utility, then there are no specific quantities of RECs that such system is required to deliver. Under the applicable supplier contract, delivery of RECs is on a portfolio basis to meet the Maximum Annual Quantity in each Delivery Year and not on a system-by-system basis. Furthermore, there are no penalties associated with delivering less of than the Maximum Annual Quantity provided, however, that you are not withholding RECs from the systems identified in the applicable supplier contract. If you do not meet the Maximum Annual Quantity, you must provide all of the RECs from the systems associated with the applicable supplier contract with the utility; you must not be withholding RECs from the utility or selling RECs from such systems to another party.
If a system we identify as part of our winning bids falls through, can we substitute another system?
No. There is no allowance for transferring a winning bid to a new system in the case that the system identified in your proposal does not materialize. In this situation, under the contract, the Bidder would forfeit the collateral associated with the RECs from such system and the project would be removed from the contract.
Can you provide highlights of what are expected to be the requirements of the DG RFP? What is the qualification form used for?
The requirements for participation in the Utility Distributed Generation request for proposals (“DG RFP”), including required documentation, will be stated in the RFP Rules which will be posted March 27, 2017 to the ‘Final Materials’ section of the Spring Utility DG page of the procurement website. The qualification form is used for you to provide the required information and upload required documents. You can register for an account to receive login credentials to use the qualification form by completing the Qualification Registration Form and selecting the “Spring Utility DG” category. Login credentials are issued the day before the Part 1 Window opens, which is March 28, 2017.
Highlights of the requirements under the DG RFP include:
- Each system presented in the proposal must be a distributed renewable energy generation device, i.e., it must be limited in nameplate capacity to 2,000 kW, behind the customer meter, and interconnected at the distribution level of an electric utility, alternative retail electric supplier, municipal utility, or a rural electric cooperative in Illinois.
- The Bidder must be either the system owner or an aggregator that has ownership of the RECs of the systems or the contractual right to legally transfer or assign RECs from the systems.
- Each bidder must provide a letter of credit in an amount of $4/REC.
- The minimum bid size is 1 MW.
- If Bids for a Bidder are approved by the Commission, the Bidder will deliver RECs to a utility under its applicable supplier contract at a single blended average price per REC for each Product (i.e., an average price for systems below 25 kW and another average price for systems between 25 and 2,000 kW). The single blended average price per REC for a Product will be calculated on the basis of the Bidder’s Bids for the RECs of that Product under contract with that utility.
- To the extent possible, 50% of RECs procured will come from systems below 25 kW.
Please also note that, to assist bidders preparing to participate in the DG RFP, the Procurement Administrator has made an early release of information and documents, including samples of documentation required in certain cases. Please consult the Final Materials page of the Spring Utility DG section of the procurement website (https://www.ipa-energyrfp.com/spring-utility-dg/final-materials/). You may also view materials of prior DG RFPs using the “Previous RFPs” link of the procurement website (https://www.ipa-energyrfp.com/previous-rfps/).
Can we include in our Proposal existing systems that are already built and energized or is the DG RFP limited to only new systems?
You can include existing systems in your Proposal. The DG RFP is not limited to new systems. For purposes of the DG RFP, an existing system means a system that has been energized as of March 28, 2017.
If our winning bids include Forecast Quantities, can we identify systems in the Large Size Class for those RECs?
No, all systems that are identified pursuant to an award of a Forecast Quantity must be from the Small Size Class.
Suppose our winning bids include a Forecast Quantity and we identify a system of the Small Size Class that is energized prior to January 28, 2018 (say on October 1, 2017). Is the system disqualified from being included in the contract because it is energized prior to January 28, 2018? If such a system can be included in the contract, can we be paid for RECs starting when it is energized on October 1, 2017?
There is no requirement for systems identified to replace Forecast Quantities to be energized only after January 28, 2018. Such a system that is energized on October 1, 2017 may be included in the contract. However, the IPA will amend the list of systems in the contract to include any such systems only once after January 28, 2018. RECs from such systems may only be transferred for payment after they have been confirmed by the IPA for inclusion in the applicable supplier contracts, which will occur after January 28, 2018 and by February 28, 2018.
Can we request an extension if a system fails to become energized by the deadline specified in the applicable supplier contract? How long is the extension? Can we also get an extension if we do not identify in time a system to replace a forecast quantity?
Any request to extend the deadline for an identified system to become energized must be made in writing to the IPA by the deadlines specified in the applicable supplier contract. Such extension may be granted at the IPA’s sole discretion but only for limited circumstances such as demonstrated delays in a utility approving interconnection of a system, or failure by the PJMGATS or M-RETS to process registration in a timely manner. Any such extension will not exceed six months and may be shorter depending on the circumstances. Please also note that no similar extension can be granted if a bidder fails to identify a system to replace a forecast quantity.
Can you provide a list of the differences between the Utility DG program and the Supplemental PV RFP?
We invite you to review the available documentation for the two programs to understand fully the differences. We highlight a few of these differences below:
The DG systems that are eligible are different:
- The Supplemental PV RFP procured RECs produced by new distributed renewable energy devices that are of solar photovoltaic technology.
- The Spring Utility DG RFP procures RECs produced by new or existing distributed renewable energy devices that may be from different technologies and are not limited to only solar photovoltaic.
The contract structure is different:
- The SPV RFP featured a structure where there was one contract associated with each system and the counterparty to the contract was the Illinois Power Agency.
- In the Utility DG RFP, there is a contract for a portfolio of systems and a winning bidder may have one or more contract with a utility (AIC, ComEd and/or MEC).
We also note that the Utility DG RFP has a minimum bid size of 1 MW and that, to the extent possible, the RFP seeks to procure 50% of RECs from systems below 25 kW.
How can I get instructions regarding payment of the Bid Participation Fee?
Please request those instructions from the Procurement Administrator at Illinois-RFP@nera.com.
I requested login credentials. Should I have received them by now?
Login credentials for the Spring Utility DG RFP have been issued. If you did not receive these credentials, please contact us at Illinois-RFP@nera.com.
Please confirm that the entity that is the Applicant of the IPA Letter of Credit can be different from the Seller that will sign the applicable DG contract with the utility.
This is correct. In the IPA Letter of Credit, the Applicant may be different from the Bidder that is indicated in Paragraph 12 of the IPA Letter of Credit. The Bidder indicated in the IPA Letter of Credit must be the Seller that will sign the applicable supplier contracts should the bids in the proposal submitted to the Procurement Event be approved.
Please confirm that the GATS or M-RETS account that is used under the applicable supplier contract for the transfer of RECs is determined by the Seller and we can indicate which GATS or M-RETS account we are using in the coversheet of the applicable Utility DG contract(s). For example, it can be the account of our parent if we do not have an account set up specifically for the Seller.
It is correct that use of PJM EIS GATS or M-RETS is required for the transfer of RECs under the applicable supplier contracts. Beyond that, the cover sheet does not require that the GATS or M-RETS account you are using for the transfer is specifically linked to the Seller name.
Please confirm that the instructions for where to send payment for REC Deliveries is determined by the Seller and we can indicate which bank account we want payment to be sent to in the coversheet of the applicable supplier contract.
You are correct. You determine where payment is to be sent under the applicable supplier contracts and you may indicate the information of your bank in the coversheet of the applicable supplier contracts.
Can we have multiple subsidiaries all bid in the Utility DG RFP?
Such a structure is likely inconsistent with the requirements of the RFP. We strongly encourage you, before having multiple subsidiaries submit a proposal, to review the requirements of the Proposal under the Utility DG RFP. For instance, as a requirement of the Proposal, a Bidder is required to make a number of certifications, including:
- The Bidder has no material information relating to the Proposal of another party;
- Other than such discussions necessary for the preparation of the Proposal, the Bidder has not disclosed, publicly or to any other party, any material information relating to the Proposal, including the systems presented as part of the Proposal; the Bids for such systems; or the Products for which Bids are presented.
We note that the fact that you are asking whether multiple subsidiaries can all bid in the same procurement event under the Utility DG RFP implies that you have knowledge of each subsidiary’s intention to submit a Proposal. It thus would appear that you would not be able to make the certifications above (and potentially other certifications required by the Proposal).
With reference to Page 9 of the Bidder Information Webcast, I see the Overall Target of 27,702 RECs. Is this the number of RECs for one year of REC deliveries or is it the Target including all years under the applicable supplier contracts?
The Overall Target of 27,702 RECs is an annual number of RECs so that 138,510 RECs (i.e., 27,702 RECs x 5 years) could be delivered under the applicable supplier contracts. The Overall Target is a total across both the Spring 2017 and Fall 2017 procurement events.
Can systems be interconnected to a distribution system of a municipal utility within Illinois?
Yes. All systems must be in Illinois and must be interconnected to the distribution system of Ameren Illinois Company, Commonwealth Edison Company, MidAmerican Energy Company, Mt. Carmel Public Utility Co., or a “municipal utility” as defined in Section 3-105 of the Illinois Public Utilities Act, or a “rural electric cooperative” as defined in Section 3-119 of the Illinois Public Utilities Act.
Can the size of systems included in the portfolio from which we deliver RECs under the applicable supplier contracts change during the term of the contract?
Yes, the final system size may be different from the planned system size indicated in your Proposal as long as the new system size does not result in a change in the Size Class of the system (e.g., from Small to Large, or vice versa). However, note that if the system size changes for one or more of your systems, this will NOT lead to a change in the maximum number of RECs that can be delivered under the applicable supplier contracts.
What is the MW equivalent of the Overall Target of 27,702 RECs annually?
The overall target can only be converted to a specific MW measure by assuming a capacity factor. However, projects of different technologies, which are all eligible for inclusion in your Proposal under the Utility DG RFP, have different capacity factors. Thus such a conversion is not straightforward; to make your own calculations, please see the capacity factors that will be used in this RFP, available in Table 1 of the RFP Rules:
What is the deadline under the applicable supplier contracts for a system included in our Proposal to deliver its first REC?
The applicable supplier contracts do not have a deadline for delivery of the first REC. Rather, the requirement for a system that is part of your winning bids is for the initial meter read date of such system to occur by May 31, 2018.
Is the Bid Participation Fee to be paid once per bidder or once per system?
The Bid Participation Fee of $500 is to be paid once per bidder for all procurement events in 2017 regardless of the number of procurement events in which you participate and regardless of the number of systems you may identify in your Proposal for the Spring 2017 procurement event under the Utility DG RFP.
If the system fails to meet its deadline for being energized and showing metered deliveries solely due to a delay in the interconnection by the utility, is the extension automatically granted?
There is no automatic extension under the terms of the applicable supplier contracts. A Seller must request an extension in writing and such extension may be granted at the IPA’s sole discretion. However, one of the circumstances specifically mentioned in the applicable supplier contracts as being a circumstance that could lead to an extension being granted is one where the Seller can demonstrate that there is a delay in the utility approving interconnection of a system. Another such circumstance is the failure by the PJMGATS or M-RETS to process registration in a timely manner.
Is the Bid Participation Fee due at the IPA’s office on April 5 or is the requirement that we initiate payment by that date?
The Part 1 Proposal, including the Bid Participation Fee at the IPA’s office, is due at 12PM (CPT) on April 5.
Where can I find the webcast presentation?
The webcast presentation is posted to the Final Materials page of the Spring Utility DG Section of the procurement website. These documents are dated March 27, 2017.
Can we sell RECs through the Utility DG RFP from systems in Iowa?
No. A condition of eligibility of a system is that it be interconnected at the distribution level of an electric utility, alternative retail electric supplier, municipal utility, or a rural electric cooperative in Illinois and thus the system must be located in Illinois.
If one of our systems under-produces in the first year of the contract, can we make up the shortfall in the second year?
REC deliveries under the applicable supplier contracts are on a portfolio basis, which means that there is an overall maximum quantity to be delivered from all the systems under that contract but there is no specific quantity maximum quantity associated to a single system. As a consequence, there is no quantity to “make up” from a particular, single system.
What is generally the end of the contract? If I have single system greater than 1 MW and the first REC Delivery from the system occurs on January 1, 2018, when does the contract expire?
The applicable supplier contracts define the end date of the contract for several different circumstances; please review, for example, Paragraph 2 on page 1 of the AIC REC Master Agreement. Generally, the expiration of the contract is five years after the date of the first REC delivery by the last system in the portfolio. In your example, if the first REC delivery of this single system occurs on January 1, 2018, the contract expires on December 31, 2022.
The structure of the program seems to incentivize developers to bid into the system and then find projects to fill their REC obligations. Is that the intent of the program?
Section 1-75(c) of the IPA Act also requires the utilities to acquire RECs from distributed generation (“DG”) devices amounting to at least 1% of each utility’s total RECs target. Please see the 2017 IPA Procurement Plan for further details on the intent of the procurement events approved under this Procurement Plan (https://www.illinois.gov/sites/ipa/Pages/2017-Procurement-Plan.aspx).
The Procurement Monitor recommended that bidders be allowed to offer “speculative RECs” in order to improve bidder response. This recommendation was incorporated into this procurement event as bidders presenting a proposal may include a Forecast Quantity of RECs to be delivered by systems that they have yet to identify.
I understand that there could be a rebate for solar photovoltaic projects. Would this rebate be available to projects interconnected to a muni or coop?
It is expected that there will be a new rebate for smart inverters for photovoltaic projects as a consequence of Public Act 99-0906 . The rebate would be provided by an electric utility that serves more than 200,000 customers in Illinois.
Can you confirm that the bank can use the following as an alternate Paragraph 14: “We, the Issuing Bank, certify that as of the Date of Issuance our senior unsecured debt is rated by at least one of Standard & Poor’s (S&P), Moody’s Investors Service (Moody’s), and Fitch Ratings (Fitch). We hereby certify that our senior unsecured debt is rated “A-” or better by S&P, or is rated “A3” or better by Moody’s, or is rated “A-” or better by Fitch. If affiliated with a foreign bank, we further certify we are a U.S. branch office of such foreign bank and that as of the Date of Issuance of this Letter of Credit, our senior unsecured debt meets the ratings requirement of this paragraph.”
Please refer to the document titled “Acceptable Modifications to the IPA LC (March 27, 2017)” posted to the Final Materials page of the Spring Utility DG section of the procurement website for all modifications to the Letter of Credit found acceptable by the IPA. The modification you have indicated above appears to be modification 14.1 found on page 21.
Is it correct that the lowest priced bid must be on the first 1 MW of systems and that after the first 1 MW of systems, we can select any bid size as long as: (i) the bid is at least 100 kW; (ii) the bid price is more than the bid price of the first 1 MW; and (iii) each system is contained fully in one block?
That is generally correct. We would add the following. First, the first block may be larger than 1 MW (it must at least 1 MW). Second, this first block may include systems of both Size Classes (and RECs for the Small Size Product may also be from a Forecast Quantity). If the first block does include RECs from both Products, then you must provide two (2) separate bid prices, i.e., one for each Product. Third, each additional block must be for only one Product (i.e., all systems must be from the Large Size Class or all systems from the Small Size Class plus any Forecast Quantity). Fourth, the bid price for an additional block for a Product (Small or Large) must be greater than the bid price for that Product in the first block.
When we identify our systems using the Worksheet Insert, what do you mean by the customer account number?
In this cell of the Worksheet Insert, please enter the customer’s account number with the electric distribution utility.
You mentioned that there are items that are requirements of the Part 1 Proposal but for which a bidder can have additional time. How much more time can we have?
Please note that additional time is only provided for new systems (energized after March 28, 2017) and additional time is provided only for some (and not all) of the required items and documents (please refer to the RFP Rules, Paragraphs IV.3.3 and IV.3.4 for details). All information required of existing systems must be provided with the Part 1 Proposal. For new systems, some items, such as the tracking system from which RECs would be transferred, can be provided by the Part 2 Date (by noon CPT on April 20).
Have the Targets and Budgets been set for the Spring DG RFP?
Specific Targets and Budgets for the Spring procurement event are set at: (i) 70% of the Overall Targets and Overall Budget for ComEd as well as for AIC; and (ii) 100% for MEC.
The “Spring Targets” for AIC, ComEd, and MEC in the Spring DG RFP are: 4,928 RECs, 14,097 RECs, and 524 RECs respectively. The “Spring Overall Target”, which is the sum of the Spring Targets across all three (3) Companies in this Spring 2017 DG RFP, is 19,549 RECs. These figures are per year.
The preliminary “Spring Budgets” for AIC, ComEd, and MEC in the Spring DG RFP are: $10,010,028, $20,486,892, and $2,971,090 respectively. The preliminary “Spring Overall Budget”, which is the sum of the preliminary Spring Budgets across all three (3) Companies in this Spring 2017 DG RFP, is $33,468,010. These figures are for all years of the applicable supplier contracts.
Final Spring Budgets will be announced no later than three (3) business days prior to Bids being due. Please see Paragraph I.2.5 through I.2.8 of the RFP Rules for more details.
I have a question about the Revenue Quality Metering accuracy metering requirements for a solar project in Illinois in the Large Size Class. I found a document on IPA website which states that all systems 25 kW and above must use a meter that meets ANSI C.12 standards. Does the ANSI C.12 imply that any 0.5 accuracy class meter is acceptable?
As part of your Proposal, you will be required to represent that: “A revenue quality meter has been or will be installed to measure the output of the system, compliant with the determination made by the Illinois Power Agency in its document “Revenue-Quality Metering Accuracy Standard and Acceptable Technologies”. The relevant document is posted here: https://www.illinois.gov/sites/ipa/Documents/IPA-metering-accuracy-standard-5-14-15.pdf.
For systems 25 kW and above registered with GATS, the requirement is that such systems utilize a meter that meets ANSI C.12 standards. For systems 25 kW and above registered with M‐RETS, the requirement is that such systems utilize an ANSI C.12 certified revenue quality meter, as may be further specified by the M-RETS operating procedures. The standard is not stated solely in terms of accuracy and does not state that all meters accurate to plus or minus 5% are acceptable. It is the responsibility of the bidder to ensure that any system presented satisfies the applicable metering standards so that the bidder can make all representations of the Proposal.
As part of our Proposal, can we commit to sell RECs from a system that is not yet built (or do we have to build the system first)?
You do not need to build the system first. However, please note that it is the bidder’s responsibility to evaluate whether the bidder can provide all the information required by the DG RFP for a system that is not yet built and it is the bidder’s responsibility to evaluate whether the timeframes for completing development, registering the system in GATS or M-RETS and having the first meter read date for the system in the applicable supplier contracts are sufficient for the bidder’s particular circumstances.
For a system that is planned but not yet built, you may present such a system as a “new” system in your Proposal. You will be required to provide information regarding the characteristics of the system. In particular, you will be required the following information regarding the system: a) system size; b) system location; c) system owner; and d) system host. (To see all information required, please refer to Paragraph IV.3.4 in the RFP Rules or see the Worksheet Insert #P1-2). You may also be asked for supporting documentation in specific circumstances. For instance, if the Owner (the owner of the system) and Host of the system (the owner of the premises where the system will be built) are not the same individual or company, you will be required to provide documentation showing that the Host agrees to the system’s installation. If this system becomes part of your winning bids, you will have to show that the system has accumulated metered deliveries by May 31, 2018 (i.e., the system has been registered in GATS or M-RETS and the initial meter read date occurs on or before May 31, 2018).
For a system that is not yet identified (in particular, you cannot provide all the information required for presenting the system as new in your Proposal), and for a system in the Small Size Class (below 25 kW), and for such a system in that Size Class only, you may present a Forecast Quantity of RECs in your Proposal. A Forecast Quantity is a quantity of RECs that you are committing to sell and that will be generated from systems that cannot yet be fully identified. If a Forecast Quantity is part of your winning bids, you will be required to fully identify the systems by January 28, 2018 and such systems must begin accumulating metered deliveries by February 28, 2019. Please note that no payment for RECs from a Forecast Quantity can be made prior to February 28, 2018.
If our bank wants to propose modifications to the Standard IPA Letter of Credit, what is the process?
You may provide comments from your bank or propose modifications to the Standard IPA Letter of Credit. Please provide such comments and or propose such modifications by submitting a redline of the Standard IPA Letter of Credit in Microsoft Word format. You may provide this document by email or by upload to the space provided in Section 5 of the online Part 1 Form. Any one of your comments or proposed modifications to the Standard IPA Letter of Credit that is found to be acceptable will be added to the list of modifications to the Standard IPA Letter of Credit approved by the IPA for use by all Bidders on an optional basis.
Where can I find the presentation from the Utility DG RFP webcast?
The webcast presentation and recording are posted to the Final Materials page of the Spring Utility DG Section of the procurement website and dated March 27, 2017.
Can you confirm that the “GATS/M-RETS system registration application and approval letter" is the only supporting document needed for an existing system?
Not necessarily. The GATS/M-RETS system registration application and approval letter is sufficient to show that the system is existing (although other documentation may be provided to confirm that the system is existing). However, there may be other documentation required based on the particular characteristics of the system. For instance, a Bidder must provide a Bidder-Owner Agreement for any system (new or existing) for which the Bidder and Owner are not the same individual or entity. More details regarding the documentation requirements can be found in Paragraph IV.3.4 of the RFP Rules. Furthermore, you can use the Documentation Insert #P1-3 as a guide to the documentation needed for your particular systems.
What documents are acceptable to show that a system is an existing system?
A Bidder including an existing system in its Proposal must provide one of the following documents to support the qualification for each existing system:
- Interconnection Agreement;
- Net metering application approval letter;
- Final system inspection confirmation;
- GATS/M-RETS system registration application and approval letter;
- permission to operate letter; or:
- other relevant documentation clearly showing the date at which the system was energized or began operation.
Email copies of the GATS/M-RETS system registration application and approval letter should be uploaded in PDF format to the spaces provided in the online form or emailed to the Procurement Administrator at Illinois-RFP@nera.com.
If we are dealing with a Host that will have multiple systems on sites that the Host owns, can we present a single Host Acknowledgment for all sites?
A single Host Acknowledgment that covers all sites is acceptable. Please make sure the single Host Acknowledgment refers to all systems that it covers.
Is there guidance available on the valuation for RECs?
The Procurement Administrator cannot provide guidance to bidders on valuations for RECs. We invite you to review the results of past procurement events under the Utility DG RFP or the SPV RFP. Results are posted to the top of each archived RFP page here:
https://www.ipa-energyrfp.com/previous-rfps/
Please note that these procurement events are for distributed generation.
I heard $3/REC during the webcast. What does this figure relate to?
The $3/REC mentioned during the webcast is the maximum amount of the supplier fee. Winning bidders pay the supplier fee within seven business days of the Commission decision on the procurement event.
I want to confirm that the maximum size of the system is 2,000 kW DC and not AC because the customer wants the system to be as large as possible.
In providing the size of the system, the bidder must provide the nameplate DC output rating of the system, expressed in kilowatts. Such size will be rounded to two (2) decimals.
Noting your comment that “the customer wants to go as large as possible”, please be aware that in presenting a system in a Proposal under the Utility Distributed Generation RFP, the system must qualify as “distributed generation”. The 2,000 kW maximum is one, but only one of the criteria for the system to qualify as distributed generation. The other criteria are:
- The system is located, or will be located when installed, on the customer side of a customer’s electric meter;
- The system is, or will be, primarily used to offset that customer’s electricity load;
- The system is or will be interconnected to the distribution system of an interconnecting distribution company in Illinois (an electric utility, alternative retail electric supplier, municipal utility, or rural electric cooperative located in Illinois).
Thus, in particular, a system that is not sized to the customer’s load and used primarily to offset that customer’s load is not eligible for the Utility DG RFP. This criterion places a second limit on the size of the system.
What are the criteria for a system to be a distributed renewable energy generation device?
For the Utility DG RFP, each system must be a distributed renewable generation device, which means that the system is:
(1) powered by wind, solar thermal energy, photovoltaic cells and panels, biodiesel, crops and untreated and unadulterated organic waste biomass, tree waste, and hydropower that does not involve new construction or significant expansion of hydropower dams;
(2) interconnected at the distribution system level of either an electric utility, an alternative retail electric supplier, a municipal utility, or a rural electric cooperative;
(3) located on the customer side of the customer’s electric meter and primarily used to offset that customer’s electricity load; and
(4) limited in nameplate capacity to no more than 2,000 kilowatts.
Are two systems installed on the same site necessarily disqualified from being bid separately into different procurement events?
Two systems that are co-located at the same site would not necessarily be disqualified from being bid separately into different procurement events. For example, if each system had its own Revenue Quality Meter and each system was behind the customer’s meter with each system with a separate utility account, then this would be acceptable.
Can you provide more information on M-RETS and GATS and their relevance for the Utility DG RFP?
M-RETS and GATS are tracking systems for RECs. Please find more information at the following websites:
Bidders with bids approved by the Commission will be required to demonstrate that each one of their systems has been registered in M-RETS or GATS and that each system has begun accumulating metered deliveries tracked by GATS or M-RETS by specific deadlines. RECs procured through this RFP will be transferred from the Supplier’s account in GATS or in M-RETS to the account of the applicable Company in the relevant tracking system. In its Worksheet Insert (#P1-2), a Bidder must identify GATS or M-RETS as the tracking system from which RECs from the system would be transferred to the Company under the applicable supplier contract.
We have several systems in our Proposal that we do not own but for which the System Owner and Host are the same entity. What happens if we gain ownership of the systems after the bidding process? If we do so, will a Host Acknowledgment be required at that time?
Please note that a Host Acknowledgement is required in the case of a new system (i.e., not energized as of March 28, 2017).
For the systems to which you refer in your question, if the System Owner and the Host are the same, but the Bidder is not the owner, you, the Bidder, will be required to provide i) a signed contract between the Bidder and the System Owner; or (ii) a letter of intent between the Bidder and the System Owner in which the System Owner agrees that it intends to give the Bidder unconditioned title to the RECs from the systems or the right to legally transfer or assign such RECs to a Company under the term of the applicable supplier contract.
All information provided and certifications made in the Part 1 Proposal, including the identity of the owner of the system, must remain valid and in full force until seventeen (17) business days after the Bid Date. During the Proposal process, once a system is marked as done, and the Bidder is notified of that fact, the Bidder may not change the information or documentation with respect to that system. If the information or documents for the system are no longer valid, the system must be withdrawn from the Proposal.
If the systems to which you refer in your question are part of bids that are approved by the Commission, and after the seventeen (17) days after the Bid Date there is a change in ownership of the system, no further documentation will be required at that time.
Can we ask the Procurement Administrator to review some of the backup documentation for our systems in advance of submitting the Part 1 Proposal? We are not using the sample document provided by the Procurement Administrator but we would like to make sure that these are nevertheless acceptable.
You may provide any such document by email to the Procurement Administrator. The Procurement Administrator endeavors to provide such courtesy review but cannot guarantee that such review will be completed before you submit your Part 1 Proposal. We may provide such courtesy review by phone with an email confirmation, saying that the documents that you provided and that we reviewed are/are not in an acceptable format.
Please note, after a courtesy review of your documents, the Procurement Administrator may nevertheless request further information regarding these documents if any aspect of these documents is not consistent with information otherwise provided in your proposal.
Can you confirm that for forecast quantities, we cannot receive payment for RECs until February 28, 2018? Can you please provide some references in the applicable supplier contract to help me understand where this is stated? Can you confirm that for systems that are identified and presented in the Proposal, we could potentially receive payment for RECs with our first invoice in July?
The applicable supplier contracts provide for the purchase of RECs from the Seller’s portfolio of systems, which include “Initial Systems” and/or “Subsequent Systems”.
Initial Systems refer to those systems that were included in the Proposal, for which information regarding system characteristics was provided, for which appropriate documentation was provided in the proposal submission process, and that were part of the bidder’s approved bids. For Initial Systems, you may deliver RECs and start receiving payment at any point after such systems have been registered in GATS or M-RETS and have an initial meter read date. (Please note that the initial meter read date must be on or prior to May 31, 2018 for each such system, otherwise the system is removed from the portfolio of eligible systems for which you may deliver RECs under the applicable supplier contract. This is discussed in Section 4(c) of the (AIC DG) REC Contract and the (MEC DG) REC Contract, and in Section 2.10(c) of the ComEd Master (DG) Agreement.) Thus, you could potentially receive payment for an invoice in July that could include, for example, RECs delivered from existing systems presented in your Proposal.
Subsequent Systems refer to those systems that are identified to replace a Forecast Quantity that was part of the bidder’s approved bids. These systems are not presented in the bidder’s Proposal and are only identified subsequent to the execution of the applicable supplier contracts. You must submit to the IPA the documents required to identify the characteristics of such systems by January 28, 2018. The IPA must confirm the addition of such systems to the portfolio of eligible systems under the applicable supplier contracts. The IPA will make one such confirmation, for all systems that are to be added to the portfolio. Such confirmation is expected to occur between January 28, 2018 and February 28, 2018. (This process is discussed in Section 4(b) of the (AIC DG) REC Contract and the (MEC DG) REC Contract, and in Section 2.10(b) of the ComEd Master (DG) Agreement.) Only once such systems are confirmed by the IPA can you deliver RECs from these systems for payment. Thus, no payment for RECs from such systems would occur prior to February 28, 2018.
We are planning to develop a system in the Large Size Class and there is one complication. The roof needs repairs before the system is installed. Can we still include the system in our Proposal? What are the deadlines for the system to be operational?
If you include this system in your Proposal, and the system becomes part of bids approved by the Commission, you will be required to complete the registration of the system in GATS or M-RETS and for the initial meter read date as recorded in GATS and M-RETS to occur by May 31, 2018. If you include this system in your Proposal, it would be considered a “new” system.
Can the entity named as the Bidder in the Proposal be different from the Applicant under the Letter of Credit?
The Bidder identified in the Part 1 Proposal must match the Bidder defined in Paragraph 12 of the Letter of Credit. However, the Applicant in the Letter of Credit may or may not be the Bidder.
Can we bid in a system that we do not own and then, if we win, assign our contract to the owner of the system?
No, as part of its Proposal, a Bidder will be required to agree to the terms of the applicable supplier contracts and to demonstrate that it has ownership of the RECs for such system or that it has the contractual right to legally transfer or assign RECs from such system to a Company. The Bidder will be the counterparty under the applicable supplier contracts for the delivery of RECs.
In the Standard IPA Letter of Credit, can Paragraph 9 explicitly reference the expiry date as a termination point of the Letter of Credit? For example, by adding a clause (c) that states that the Letter of Credit will terminate on the earliest of: “(a) the date you have made drawings which exhaust the amount available to be drawn under this Letter of Credit; or (b) the date we receive from you a Certificate of Cancellation in the form of Annex 3 hereto together with the original of this Letter of Credit (and subsequent amendments, if any) returned for cancellation; or: (c) the Stated Expiry Date?
Paragraph 1 of the Letter of Credit states:
“It is a condition of this Letter of Credit that it shall be deemed automatically extended, without amendment, for additional period(s) of 364 days from the expiration date hereof, or any future expiration date”
By proposing to add the condition to Paragraph 9 of the Letter of Credit that the Letter of Credit will expire on “the Stated Expiry Date”, you directly contradict the terms in Paragraph 1. The Letter of Credit cannot both be: (i) automatically renewing for an additional year and (ii) terminate on the stated expiration date, which will be one year from issuance. As such, this proposed modification, and any modification similar in concept, is unacceptable.
With an automatic renewal of the Letter of Credit, does it mean that the Letter of Credit is potentially valid in perpetuity?
No, this does not mean that the Letter of Credit would remain valid in perpetuity; it just means that the exact termination date is subject to uncertainty because it depends on the Bidder’s exact circumstances. These circumstances are detailed in the RFP Rules and summarized here for your convenience, with approximate dates.
If you do not have bids that are approved by the Commission, the Letter of Credit will be returned as soon as practicable after the Commission decision (expected May 3, 2017). If you have bids approved by the Commission, the amount of the Letter of Credit is reduced to match the number of RECs in your winning bids as soon as the Supplier Fees are paid (7 business days after the Commission decision, expected May 12, 2017). The Letter of Credit is then further reduced as you show that your systems are producing RECs. Specifically:
- If all your systems are existing and you are not bidding Forecast Quantities, one would expect that all your systems will demonstrate that they have accumulated metered deliveries by the end of the first quarter under the contract, at which point the Letter of Credit would be returned (approximately July 31, 2017).
- If some of your systems are new but you are not bidding Forecast Quantities, the new systems must be registered in GATS or M-RETS and have the initial meter read date recorded in GATS and M-RETS by May 31, 2018. In that case, the Letter of Credit would be returned by the end of the next quarter, approximately July 31, 2018.
- If you are bidding Forecast Quantities, the Letter of Credit expires and is returned when all systems must be identified and all such systems must be registered in GATS or M-RETS and have had their initial meter read date by February 28, 2019. In that case, the Letter of Credit would be returned by the end of the next quarter, approximately March 31, 2019.
Note that, under the terms of the applicable supplier contracts, a bidder may ask for an extension for a system to become energized. This could lead to a later return of the Letter of Credit. However, such an extension, if it is granted, will not exceed six months.
Can co-located systems be considered separate systems for purposes of bidding in the procurement event? What other conditions should we be aware of?
Systems that are co-located can be considered to be separate systems for purposes of bidding in the procurement event as long as each system has its own separate revenue quality meter and has its own identifier in the applicable tracking system (GATS or M-RETS).
Such systems must also meet the interconnection conditions of the applicable utility and, as a distributed renewable generation device, must be located on the customer side of the customer’s electric meter and be primarily used to offset that customer’s electricity load.
If we are not including Forecast Quantities in our Proposal, do we still need to submit the Speculative Insert (#P1-4)?
No. This Insert only applies if you wish to include Forecast Quantities in your Proposal.
In Section 4 of the Part 1 Form, we are asked for our forecast quantity. Is this quantity a number of RECs or a number of kW? Is this quantity annual or for the entire duration of the applicable supplier contracts?
The Forecast Quantity is a quantity of RECs that you expect to be produced by systems that you have not yet identified during a single year.
How should we calculate the annual number of RECs that will be our Forecast Quantity?
You should calculate the number of RECs that you expect the systems that you have not yet identified to produce annually. For a given system, you can calculate the number of RECs as follows:
(size of system in MW) x (capacity factor for specific technology) x 8760
For example, if you have not yet identified but anticipate a 100 kW photovoltaic system (fixed mount), this would be:
(0.1) x (0.1438) x 8760 = 126 (rounded from 125.97)
If you provide a Forecast Quantity, the Procurement Administrator uses a capacity factor of 14.38% to calculate the associated capacity for purposes of verifying that you meet the 1 MW minimum bid. For example, if you have not identified but anticipate a 100 kW tracking photovoltaic system, the annual RECs would be:
(0.1) x (0.1700) x 8760 = 149 (rounded from 148.92)
The capacity that the Procurement Administrator will associate with a Forecast Quantity of 149 will be:
149 / (0.1438 x 8760) = .11828 MW or 118.28 kW
An existing system can be presented in the DG RFP. Does that include systems that are under contract with the IPA pursuant to another procurement event (for example, a procurement event under the SPV RFP)?
No. Systems that are under contract, either with the IPA pursuant to a procurement event under the SPV RFP, or with a utility pursuant to a procurement event under the DG RFP, cannot be presented as part of your Proposal in the Spring 2017 Utility DG RFP.
Can we still submit comments or proposed modifications on the Standard IPA Letter of Credit?
Yes. The Procurement Administrator will continue to process comments or proposed modifications for all submissions received by 12 PM (noon) CPT on April 12, 2017.
We are presenting some systems that we acquired after the systems had received their GATS approval. Thus, we do not have the approval letter. However, for purposes of documenting the fact that the system is existing, we can provide an Excel file from the GATS website showing that the system has been approved by GATS. Will that be acceptable?
The GATS approval Excel file will be accepted as the approval letter in your particular circumstances.
In Paragraph 9 of the Standard IPA Letter of Credit, can we add “the expiration date of the Letter of Credit in accordance with Paragraph 1” as an event of termination?
The IPA has reviewed this proposed modification and found it not to be acceptable.
Your bank may want to consider acceptable modification 1.4, provided below for your convenience.
We, ______________(the “Issuing Bank”), hereby establish this Irrevocable Standby Letter of Credit (this “Letter of Credit”) in your favor in the amount of USD $________________, effective immediately and available to you at sight upon demand at our counters at ________________[designate Issuing Bank’s location for presentments]. This Letter of Credit shall expire 364 days from date of issuance, unless terminated earlier in accordance with the provisions of Paragraph 9 hereof, or otherwise extended. It is a condition of this Letter of Credit that it shall be deemed automatically extended, without amendment, for up to two additional period(s) of 364 days from the expiration date hereof, or any future expiration date, unless at least ninety (90) days before its current expiration date, we send notice to you in writing by registered mail or overnight courier at the address above, and we send notice to the Applicant, that we do not intend to extend this Letter of Credit.
Where can I find information and documents regarding the Fall 2017 Distributed Generation RFP?
Information regarding the Fall 2017 Distributed Generation RFP has not yet been released. As guidance you may review the Spring 2017 Distributed Generation RFP documents, which are available here:
https://www.ipa-energyrfp.com/spring-utility-dg/final-materials/
Please note that some aspects of the RFP may change for the Fall procurement event.
What is an Agency Agreement?
An Agency Agreement is a contractual relationship whereby one entity (the “agent”) acts on behalf of one or more other entities (the “principals”) in regards to the specific business specified in the agreement.
We have a system that spans two buildings and is behind the meter of two different customers. The system has a single GATS account. For purposes of the DG RFP, do we present this as one or two systems?
With a single GATS account, this should be considered to be one system.
What should be the amount of the Letter of Credit?
A Bidder must, with its Part 2 Proposal, submit an executed Letter of Credit in the amount of $4 times the number of RECs that the Bidder can win across all systems and the total Forecast Quantity across all delivery years under the applicable supplier contracts. Please note that Attachment 5 to the Part 1 Notification, which was re-issued to all bidders with a correction, includes the required amount of the Letter of Credit assuming you intend to bid on all identified systems and the total Forecast Quantity that you presented in your Part 1 Proposal.
Can you provide some examples of how to calculate the required amount for the Letter of Credit?
We provide two examples of the calculations for the required amount for the Letter of Credit, strictly for illustrative purposes.
Example 1. A Bidder presents no identified systems and a total Forecast Quantity of 2,000 RECs. Since this is an annual quantity of RECs, to support the bids, the Letter of Credit must be in an amount of at least:
2,000 RECs x 5 contract years x $4 = $40,000.
Example 2. A Bidder presents a 1 MW solar photovoltaic system (fixed mount) in its Part 1 Proposal. The annual quantity of RECs associated with this system is:
Annual quantity of RECs = 1 MW x 0.1438 capacity factor x 8,760 hours/yr = 1,259.688 RECs
The result is rounded to the nearest REC, i.e., 1,260 RECs, and it represents an annual quantity of RECs. If the Bidder has multiple systems, the Bidder would calculate the number of RECs for each system and round the result for each system separately.
Since this is an annual quantity of RECs, to support the bids, the Letter of Credit must be in an amount of at least:
Required Letter of Credit amount = 1,260 RECs x 5 contract years x $4 = $25,200.
Is the entity named as the Bidder in the Part 1 Proposal required to also be the entity that would sign the applicable supplier contracts if the Bidder has bids approved by the Commission?
Yes. With respect to signing the applicable supplier contracts, the entity named as the Bidder in the Part 1 Proposal must be the party that executes the applicable supplier contracts if the Bidder has bids approved by the Commission.
Is the entity named as the Bidder in the Part 1 Proposal required to also be the Applicant for the Letter of Credit?
No. With respect to the Letter of Credit, the entity named as the Bidder in the Part 1 Proposal must be identified as such in Paragraph 12 of the Letter of Credit. However, the Applicant, and the entity named in Paragraph 1 of the Letter of Credit, may or may not be the Bidder.
The System Owner and the Bidder are different entities. Do we need a letter of intent stating that we have ownership of the RECs from the system?
Any information or documentation that is still required of you to support identified systems is listed in your Part 1 Complete Notice. If, for a given system, the Bidder and System Owner are not the same individual or entity and you have not yet provided a Letter of Intent or other supporting document to show that the Bidder has ownership of the RECs, you will be required to do so by the Part 2 Date, April 20, 2017 at 12 pm (noon) CPT.
For one of the systems we present in our Proposal, the Host and System Owner are the same. What documentation will be required (if any) if the ownership of that system is transferred from the Host to us after we win the bid?
All information provided and certifications made in the Proposal, including the identity of the owner of the system, must remain valid and in full force until seventeen (17) business days after the Bid Date. If the systems to which you refer in your question are part of bids that are approved by the Commission, and after the seventeen (17) days after the Bid Date there is a change in ownership of the system, no further documentation will be required at that time.
Can we submit a check or cash instead of the Letter of Credit?
The IPA will not accept cash or a check to meet collateral requirements for the Utility DG RFP. All bidders must submit a Letter of Credit with their Part 2 Proposal either in the form of the Standard IPA Letter of Credit or using only modifications acceptable to the IPA and posted to the procurement website.
The bank is issuing our Letter of Credit but they cannot promise that it will be received by the IPA by the deadline of 12 PM (noon) CPT on April 20. Will our Part 2 Proposal be automatically rejected?
If your original Letter of Credit is not received by the IPA by the Part 2 Date of 12 PM (noon) CPT on April 20, 2017, you will be given two business days (until 6 PM CPT on April 24) to cure this deficiency. If you do not provide any response by the deadline provided to you, your Part 2 Proposal will be rejected.
Can we change the identity of the bidder at the Part 2 Proposal stage?
The bidder in the Part 2 Proposal must be the same as the entity identified as the bidder in the Part 1 Proposal.
Can we submit the supplier fees at this time or must we wait until there is a decision of the Commission on the results of the procurement event and the IPA sends us an invoice?
You must wait to receive an invoice from the IPA with the exact amount of the supplier fees as well as full payment instructions before submitting payment. Supplier fees cannot be paid at this time.
Should we contact the IPA or GATS for meter-read verification procedures?
Please contact GATS directly regarding meter-read verification procedures:
(877) 750-GATS (4287)
Are the payments under the applicable supplier contracts based on the RECs actually produced by our solar systems or based on the RECs that would be expected from these systems given their sizes and the capacity factors? If based on actual production, what would happen in an extremely cloudy year?
Under the applicable supplier contracts, payments are based on RECs delivered (so, the production of all the systems under contract, subject to the Maximum Annual Quantity in each Delivery Year). The applicable supplier contracts are structured on a portfolio basis and are not structured on a system-by-system basis. The applicable supplier contract will specify a Maximum Annual Quantity to be delivered, which can be supplied from any of the systems identified as part of the approved bids (or identified subsequently if the approved bids initially specified a forecast quantity) and allocated to the applicable supplier contract with the utility.
If it is an extremely cloudy year and all of your systems produce less than expected, there are two consequences. First, REC payments will be based only on the RECs that you deliver, so that these payments may be lower than those associated with the Maximum Annual Quantity. Second, if you do not deliver up to the Maximum Annual Quantity, you must provide all of the RECs produced by the systems associated with the applicable supplier contract with the utility; you must not be withholding RECs from the utility or selling RECs from such systems to another party. Such action would be a condition of default under the applicable supplier contracts.
Will the IPA accept payment of the supplier fees by wire transfer or must we pay by check?
The IPA does not accept payment via wire transfer but does accept payment by check. Supplier fees are paid only by suppliers with bids approved by the Illinois Commerce Commission (“ICC”). The ICC is expected to render a decision on the results of the procurement event on May 3, 2017. Instructions for payment of the supplier fees will be sent to suppliers with approved bids at that time.
What are the supplier fees? Were these announced on schedule?
The supplier fee is $3 per REC for the quantity of RECs associated with winning Bids across all Delivery Years. The supplier fee per REC was announced on April 25, 2017 within the deadline provided by the RFP Rules.
If our First Block includes systems from both Size Classes, is it the case that either all of our systems from both Size Classes will be selected or none of them will be selected?
If your First Block includes RECs from both Size Classes, you are required to submit two Bid prices, one for each Product (i.e., one for RECs from the Small Size Class and one for RECs from the Large Size Class). These Bid prices will be evaluated separately. It is not the case that the entire block is evaluated on a blended price basis. Thus, it is possible for the evaluation of Bids to select the portion of your First Block for one Size Class and not the portion from the other Size Class.
What happens if the actual size of one of our systems turns out to be less than expected? Does this lead to a draw on the Letter of Credit?
The final system size may be different from the planned system size indicated in your Proposal as long as the new system size does not result in a change in the Size Class of the system (e.g., from Small to Large, or vice versa). This does not in itself lead to a draw on the Letter of Credit (although if you fail to identify sufficient capacity to correspond to the forecast quantity you bid, this could lead to a draw on the Letter of Credit).
Please note that if the system size is reduced for one or more of your systems, this will NOT lead to a reduction in the Maximum Annual Quantity, which is the number of RECs expected to be delivered under the applicable supplier contracts. If you do not deliver the Maximum Annual Quantity, there is no penalty under the applicable supplier contracts as long as you provide all of the RECs from the systems associated with the applicable supplier contract with the utility. You must not be withholding RECs from the utility or selling RECs from such systems to another party (such action would be a condition of default under the applicable supplier contract).
Are wind resources eligible to bid in the IPA’s procurement events? Can I still participate in the Spring 2017 procurement event?
The Utility Distributed Generation RFP (“DG RFP”) solicits suppliers to deliver RECs generated from distributed generation systems to AIC, to ComEd, or to MEC (each a “Company”) or to any combination of these three (3) Companies. Such device may be powered by wind, solar thermal energy, photovoltaic cells and panels, biodiesel, crops and untreated and unadulterated organic waste biomass, tree waste, and hydropower that does not involve new construction or significant expansion of hydropower dams.
The deadlines for the Spring 2017 DG RFP have passed. There will be a second procurement event in the Fall. While the specifics of the requirements may change at that time, please consult the RFP Rules posted to the Final Materials page of the Spring Utility DG section of the procurement website for details regarding the qualification process and requirements for participation.
If the wind projects to which you are referring are not distributed generation devices, please review information regarding the Initial Forward Procurement as it becomes available. That procurement event has an expected bid date of August 10, 2017 (which would place the start of activities under this procurement event in June).
Could a party be prevented from participating in the IPA’s procurement events because of an on-going lawsuit?
It is unclear to us the procurement event to which you refer. Any such requirements would be representations under the applicable supplier contracts regarding the party’s ability to perform. Please review the supplier contracts applicable to the procurement event to which you are referring for additional information.
I understand that if we have bids that are approved by the Commission, we may be required to signed the applicable supplier contract with more than one utility. Is it possible that a block that is part of our approved bids would be split across two contracts?
The RFP Rules specify that in no case will the allocation of approved Bids result in the RECs from a given system being delivered to more than one Company. To the extent possible, the allocation of approved Bids will avoid RECs from a given block being delivered to more than one Company. However, if required to satisfy the Target for MEC, it is possible that such a situation could occur.
Will the Fall Utility DG RFP bidding process, parameters, and requirements be the same as the Spring Utility DG RFP?
The Procurement Administrator expects to provide draft documents or a release of parameters for the Fall Utility DG RFP in August 2017. Please check back at that time for additional information about this upcoming RFP.
I am clicking on the results page for the DG RFP. It is blank. Where can I find the results of the Spring DG RFP?
The results of the Spring 2017 Utility Distributed Generation RFP (“DG RFP”) have been archived here: https://www.ipa-energyrfp.com/2017-distributed-generation-rfp/
You are likely clicking on the results page for the Fall 2017 DG RFP, which will be populated only when those results become available.
My understanding is that the Utility DG RFP had a total budget of $46,538,119 (over 5 years), and intended to procure 27,702 RECs per year. Will the RECs procured in the Spring DG procurement event be subtracted from these totals in determining the Target and Budget for the Fall DG procurement event? Are those figures available now?
The DG procurement events for 2017 (both Spring and Fall) had a preliminary Overall Budget of $46,538,119 which spans the five years of the contract. The DG procurement events had a preliminary Overall Target of 27,702 RECs on an annual basis. Of the overall Target of 27,702 RECs, a Spring Target of 19,549 RECs was established, all of which were procured in the Spring Utility DG procurement event.
The number of RECs procured in the Spring DG procurement event and the budget associated with these RECs will be subtracted from the Overall Target and Budget. However, the Overall Target and Budget are subject to revision. The Target and Budget applicable to the Fall Utility DG procurement event will be announced in the coming weeks. If you have not done so already, please register to receive our announcements.
Would it be possible for a winning bidder in the Spring Utility DG RFP to use the letter of credit it holds with the IPA for purposes of providing the financial guarantees that are required in the Fall Utility DG RFP? What amendment would be required in that case?
Thank you for your comment, which we will incorporate as we finalize the Fall 2017 DG RFP. A Bidder that already holds a letter of credit with the IPA that was submitted under the Spring Utility DG RFP will be able to use this same letter of credit for purposes of providing the financial guarantees required by the Part 2 Proposal under the Fall Utility DG RFP. Such Bidder will be required to provide an amendment to increase the value of the letter of credit and to change the expiration date. Detailed instructions will be available from the Procurement Administrator prior to the Part 2 Window.
Did the Procurement Administrator make the early information release for the DG RFP?
The Early Information Release for the DG RFP was posted on July 28, 2017 to the Draft Documents page of the procurement website.
Does the 2 MW (AC rating) limit apply per building, per account, or per meter? Is it possible to present multiple systems that are in close proximity?
Any individual system presented as part of a Proposal for the Utility DG RFP (“DG RGP”) is limited in size to 2,000 kW nameplate capacity (AC rating). An individual system is defined by its own separate revenue quality meter and its own identifier in the applicable tracking system (GATS or M-RETS). Thus, it is possible to present multiple systems that are in close proximity as long as each system has its own revenue quality meter and is separately identified in the applicable tracking system. Furthermore, any system in this procurement event must also meet the interconnection conditions of the applicable utility and, as a distributed renewable generation device, must be located on the customer side of the customer’s electric meter and be primarily used to offset that customer’s electricity load.
What was the list of winning suppliers in the Spring 2017 Utility DG procurement event? How can I find the list of winning suppliers for previous DG procurement events?
The list of winning suppliers for the Spring 2017 Utility DG procurement event is as follows: Ameresco Inc.; Carbon Solutions Group LLC; IL-Solar, Inc; SoCore Installation Services LLC; Solar Star Illinois I, LLC; and SRECTrade, Inc.
Generally, the list of winning suppliers is provided as part of an information release following the Commission decision on the procurement event. To access these information releases, please go to the procurement website, https://www.ipa-energyrfp.com/, click on “Previous RFPs” in the left-hand navigation bar, then click on the procurement event that interests you. There were some distributed generation RFPs prior to 2017. Once on the page of the procurement event of interest, there will be an “RFP Results” heading under which you can find the information release.
I am reading the documents and I am seeing various references to systems below 25 kW. Must all systems that we present in the DG RFP be below 25 kW or is there some kind of priority given to smaller systems?
No, systems 25 kW or over can be presented in Proposals for the DG RFP. The limit on the size of a system is a nameplate capacity of 2,000 kW (AC rating).
There are references to systems under 25 kW because there are two (2) “Products” in the DG RFP, each defined by the “Size Class” of the system that generates the RECs. Systems in the “Small Size Class” are systems under 25 kW in nameplate capacity (AC rating). The “Small Size Product” consists of RECs generated from systems in the Small Size Class. Systems in the “Large Size Class” are systems of at least 25 kW but no more than 2,000 kW in nameplate capacity (AC rating). The “Large Size Product” consists of RECs generated from systems in the Large Size Class.
To the extent possible, 50% of RECs procured will come from the Small Size Product.
Is there a maximum on the number of RECs that a Bidder can bid through the DG RFP?
Yes. There is an “Overall Target” for the procurement event of 8,153 RECs (annually). This “Overall Target” is the sum of a Target for AIC of 1,614 RECs and a Target for ComEd of 6,539 RECs. A Bidder can, for the Large Size Class (systems 25 kW or above), present systems that together produce an annual quantity of RECs up to and including the Overall Target. Similarly, for the Small Size Class (systems below 25 kW), a Bidder can present systems and a forecast quantity that together produce an annual quantity of RECs up to and including the Overall Target. (A Bidder can bid both up to the Overall Target for the Large Size Class and for the Small Size Class).
Are the quantities for future procurement events under the Utility Distributed Generation RFP known at this time? Is it known how many procurement events there will be?
The Illinois Power Agency expects to release a draft Long-Term Renewable Resources Procurement Plan in September 2017, which will be subject to review by the Illinois Commerce Commission. Information about future procurement events under the DG RFP will become available after such review has concluded.
Are the final capacity factors available?
The final capacity factors are available in the Parameter and Process Information Release posted to the Final Materials page of the Fall Utility DG section of the procurement website.
Has the amount of the Supplier Fee been released?
The Procurement Administrator has released early an estimate of the Supplier Fee, which is $7/REC. The Procurement Administrator does not expect to be able to provide an update to this estimate prior to the submission of the Part 1 Proposals. The exact amount of the Supplier Fee per REC will be announced no later than two (2) business days before the Bid Date.
What is the amount of the letter of credit that will be required? Does it depend on the level of the Supplier Fee?
The amount of the Letter of Credit is completely unrelated to the supplier fees. Each Bidder will be required to submit a Letter of Credit in an amount of $4 times the number of RECs that the Bidder can win across all systems and the total Forecast Quantity across all delivery years under the applicable supplier contracts. A Bidder that already holds a letter of credit with the IPA will have the option to provide an amendment to this letter of credit to increase the value of the letter of credit and to change the expiration date instead of having a new letter of credit issued for purposes of providing the financial guarantees required by the Part 2 Proposal. The final Letter of Credit and initial list of acceptable modifications were posted to the procurement website on August 15, 2017.
How are the Annual Quantity and Maximum Contract Quantity calculated? When does rounding occur (when the Annual Quantity is calculated or when the Maximum Contract Quantity is calculated)?
The formula is described in the Parameter and Process Information Release posted to the Final Materials page of the Fall Utility DG section of the procurement website on August 15, 2017.
The Annual Quantity is calculated as the product of (a) the planned installed size of the system in kW divided by 1,000; and (b) the capacity factor associated with the technology of the system; and (c) 8760 hours. The result is rounded to the nearest REC. Thus, rounding occurs in the calculation of the Annual Quantity for a particular system. The overall Maximum Contract Quantity over the entire term of the applicable supplier contract for a system is obtained by multiplying the Annual Quantity (already rounded to the nearest REC) by five (5) years.
How is the nameplate capacity (AC rating) for a system calculated?
The calculation is described in the Parameter and Process Information Release posted to the Final Materials page of the Fall Utility DG section of the procurement website on August 15, 2017. The nameplate capacity (AC rating) for a system is measured by summing the nameplate AC ratings of the project’s inverters.
Is the Host Acknowledgement Form required of new systems, existing systems or both? When is the Host Acknowledgment Form due?
The Host Acknowledgement is required only for the new systems and it is due by the Part 1 Date. If the document is not available at that time, the Bidder must justify this omission in the Part 1 Proposal. The Bidder will then be given more time to provide the document within the Part 2 Window. However, in no event will a Bidder be allowed to submit the Host Acknowledgment or to complete any other missing information regarding its systems after 12 PM (noon) CPT on the third business day prior to the Bid Date.
Can you clarify whether the total number of solar renewable energy credits (“SRECs”) that will be procured in the procurement event under the Fall 2017 DG RFP, which is 40,765, is an annual number of SRECs or a number of SRECs over the five-year term of the applicable supplier contract?
The annual target for the upcoming procurement event under the Fall 2017 DG RFP is 8,153 RECs. The total number of RECs to be procured over the five (5) year contract term is 40,765 RECs.
The target for the upcoming procurement event is an overall target for all technologies allowed under the DG RFP (solar thermal energy, photovoltaic cells and panels, wind, biodiesel, crops and untreated and unadulterated organic waste biomass, tree waste, and hydropower that does not involve new construction or significant expansion of hydropower dams). There is no separate target for solar renewable energy credits.
I am about to have a 7kW array installed on my residence. Can I participate in the Adjustable Block Program and/or the procurement event under the Fall 2017 DG RFP?
Details regarding the adjustable block program are not available at this time. The adjustable block program will be first proposed in the Illinois Power Agency’s long-term renewable resources procurement plan (due to be released within 120 days of June 1, 2017) with the Illinois Commerce Commission having final approval of the details of the program.
There is a procurement event planned for this Fall under the Distributed Generation RFP. However, there is a minimum bid size requirement of 1 MW. Small systems can participate through an aggregator. The list of winning suppliers for the Spring 2017 Utility DG procurement event was: Ameresco Inc.; Carbon Solutions Group LLC; IL-Solar, Inc; SoCore Installation Services LLC; Solar Star Illinois I, LLC; and SRECTrade, Inc. Generally, the list of winning suppliers is provided as part of an information release following the Commission decision on the procurement event. To access these information releases, please go to the procurement website, https://www.ipa-energyrfp.com/, click on “Previous RFPs” in the left-hand navigation bar, then click on the procurement event that interests you. There were some distributed generation RFPs prior to 2017. Once on the page of the procurement event of interest, there will be an “RFP Results” heading under which you can find the information release.
The purpose of this website is to provide information to suppliers participating in the IPA’s procurement event. The Illinois Solar Energy Association has information for homeowners generally: http://www.illinoissolar.org/Procurement.
Can you confirm that the document provided in FAQ-DG-64 providing the standards for metering accuracy is still the correct document?
Yes, this is the correct document.
For purposes of qualifying a system into the DG RFP, can the system be connected to an electric cooperative?
There is a minimum bid size requirement of 1 MW and thus small systems participate in the Utility DG RFP through an aggregator. A distributed generation system must be interconnected at the distribution level of an electric utility, a municipal utility that owns or operates electric distribution facilities, or a rural electric cooperative as defined in the Public Utilities Act.
It is my understanding that if we are presenting a system that qualified in Spring 2017, all we have to do is to email the AC rating size of the system to the Procurement Administrator and to update the letter of credit. How do we update our bids?
We would like to clarify that while you will not have to provide information on the system characteristics anew or to resubmit documents regarding a system presented in the Spring 2017 DG RFP to the extent that all such information remains valid, you will still be required to present a Part 1 Proposal and a Part 2 Proposal that satisfy all the requirements of the Utility DG RFP, including presenting at least 1 MW of systems, making all certifications required, and presenting your bids in accordance with the instructions provided by the Procurement Administrator. Full requirements will be available when the RFP is issued on September 7, 2017.
For the DG RFP, does a Bidder submit a single Proposal for all its Projects or is the Bidder required to submit a separate Proposal for each of its Projects?
Each Bidder submits a single Proposal in the DG RFP and through this Proposal the Bidder provides information about all of its Projects. There is a minimum bid size requirement: the Proposal must include systems that together are the equivalent to at least 1 MW (AC rating) in size.
Does each Bidder have a single set of login credentials to access all the online forms for the different RFPs or is there one set of login credentials for each RFP?
Generally Bidders are issued different login credentials to access the online forms for each RFP. If you participated in another RFP in 2017, please request new credentials for access to the online forms for the DG RFP.
What documentation can be provided by the Part 2 Date if such documentation is not available during the Part 1 Window?
In the Part 1 Proposal, you are asked to provide all necessary documentation regarding the characteristics of a Project. To the extent that the following documentation is not available during the Part 1 Window:
- Documentation to demonstrate that the Bidder has ownership or title to the RECs, such as Letters of Intent, for new and existing systems for which the Bidder is not the System Owner;
- Documentation to demonstrate that the system was energized and registered in GATS or M-RETS as of September 18, 2017 for existing systems;
- Documentation by which the Host acknowledges installation of the system on the Host’s premises for new systems for which the System Owner is not the Host.
Then the Bidder will be required to provide such documentation by the Part 2 Date.
We are providing documentation from GATS to show that a system is existing, i.e., energized and registered through GATS. The size on the GATS documentation is nameplate capacity (DC rating). Is the Bidder required to explain the discrepancy between the DC rating in the GATS documentation and the AC rating provided in the Worksheet Insert?
The Procurement Administrator acknowledges that the system size provided on GATS documentation provided with the Part 1 Proposal is based on nameplate capacity (DC rating) and will not be identical to the system size based on size (AC rating) in the Worksheet Insert (#P1-2). The Procurement Administrator does not require the Bidder to explain the difference between the DC rating and the AC rating. However, the Procurement Administrator may ask for additional information if the DC and AC ratings do not appear consistent with each other, for example because the ratio of the DC to AC ratings is not consistent with industry norms, which may indicate an error in the AC rating or the documentation provided.
What is the total capacity procured in the Fall 2017 DG RFP?
The Overall Target for the Fall 2017 DG RFP is 8,153 RECs. This represents approximately 5.5 MW using the capacity factor for solar photovoltaic cells and panels (fixed mount), of which approximately 4.4 MW is for ComEd’s portfolio, and the rest for AIC’s . However, the actual capacity procured may differ from these figures as the Targets can be met by procuring RECs from various resources, with varying capacity factors.
A requirement of the DG RFP is that systems installed after June 1, 2017 be installed by “qualified persons.” Where is "qualified person" defined?
The term “qualified person” is defined by subsection (i) of Section 1-56 of the Illinois Power Act. It is the responsibility of the Bidder to review the requirements for the installation by qualified person in the Act.
What is the required minimum bid size?
The required minimum bid size is 1 MW (AC rating).
The Procurement Administrator converts the capacity of the system into an annual quantity of RECs. Does the Procurement Administrator use the AC or DC rating to make that calculation?
The size of the system (AC rating) is used in all calculations and references in the DG RFP.
Do the Bid Participation Fee and the Supplier Fees go towards covering the costs for the procurement event? When is the Letter of Credit required?
The Bid Participation Fee and the Supplier Fees are used to cover the costs of the procurement event. All Bidders must pay a Bid Participation Fee once during the year to participate in the IPA procurement events. The Supplier Fees are levied only on Bidders that have Bids approved by the ICC. Each Bidder is required to post a Letter of Credit with the Part 2 Proposal. This Letter of Credit serves as bid assurance collateral and also remains in place during the term of the applicable supplier contracts until all Forecast Quantities are converted into identified systems and all identified systems have delivered at least one REC.
After the term of the contract expires, who owns the RECs for the systems that were under contract? Can RECs from those systems be bid into other procurement events?
During and after the term of the applicable supplier contract, the Owner of the systems owns the RECs from the system. During the term of the applicable supplier contract, the Seller delivers and transfers the RECs to the Company or Companies in quantities sufficient to satisfy its obligations. After the term of the contract ends, the Owner of the system is free to avail itself of other opportunities to sell the RECs from the systems.
Will previously qualified Bidders be required to provide the P1-1 Representative Insert if it was provided in the last procurement event?
A Bidder that successfully completed the Part 1 Proposal for a prior procurement event under a Distributed Generation RFP is said to have “previously qualified”. A previously qualified Bidder must review the contact information for the Bidder and the representative of the Bidder and must update this information accordingly. All Bidders, whether previously qualified or not, will need to provide the Representative Insert (#P1-1) if such Bidder wishes to designate additional Representatives to be copied on all communications from the Procurement Administrator.
If we are amending a Letter of Credit that we currently have with the IPA, what should be the new expiration date?
The expiration date specified in the amendment should be 364 days or one year from the date of the issuance of the amendment.
We adopted an acceptable modification for the Letter of Credit that we currently have with the IPA and it is unclear to us how to modify the expiration date. Can you provide guidance on this issue?
We understand that the language in an existing Letter of Credit may be different across Bidders, as some Bidders may have elected to use an acceptable modification in the prior procurement event. Bidders can contact the Procurement Administrator for instructions related to the specific language of their Letter of Credit.
Should the bid assurance collateral be sent to the Companies (AIC and ComEd but not MEC)?
The bid assurance collateral must be in the form of a Letter of Credit with the IPA as beneficiary. Bid assurance collateral is NOT sent to the Companies that are purchasing through this procurement event. It is correct that AIC and ComEd but not MEC are purchasing RECs through this procurement event.
Is it possible to be a winner for a portion of a Block that we bid? If so, will the bidder be able to select the systems that would be under contract?
Yes, it is possible that a winning bid that is identified and approved by the ICC is for just a fraction or portion of the RECs bid in a Block. If this does happen, a Bidder will be asked to select the systems that will be part of the applicable supplier contract to the extent that the Bidder chooses to accept the partial award.
If production from the systems falls short of the contracted Annual REC quantity, does the contract extend into an additional year to provide an opportunity for the seller to make up the deliveries?
No, there is no opportunity to make up deliveries if the systems fail to deliver the contracted quantities. Please review the terms under each applicable supplier contract posted to the Final Materials page of the Fall Utility DG section of the IPA procurement website for additional information regarding consequences of being unable to deliver the annual quantity of RECs under each contract.
What is the relationship between the Fall DG RFP and the IPA’s long-term renewable plan?
The Fall 2017 DG RFP relates to the IPA’s Procurement Plan filed on September 27, 2016 and approved by the Illinois Commerce Commission in Docket No. 16-0453. Additional information regarding the long-term renewable plan will be posted to the IPA’s website as it becomes available. Please see:
https://www.illinois.gov/sites/ipa/Pages/Plans-Under-Development.aspx
How many RECs were procured in the Spring 2017 DG RFP?
19,549 RECs were procured in the Spring 2017 DG RFP. The complete results are available here:
https://www.ipa-energyrfp.com/2017-distributed-generation-rfp/
Where can I get information about the IPA’s procurement plans for 2018?
The information for the IPA’s procurement plans under development is posted here:
https://www.illinois.gov/sites/ipa/Pages/Plans-Under-Development.aspx
Is it correct that the Fall 2017 DG RFP will only procure RECs for AIC and ComEd and not for MEC?
Correct. The Fall 2017 DG RFP seeks to procure RECs for AIC and ComEd; RECs will not be procured for MEC in this procurement event.
Given that RECs will only be procured for AIC and ComEd through the Fall 2017 DG RFP, does it mean that Bidders only need to provide bid assurance collateral to these two Companies?
In the DG RFP, bid assurance collateral is provided to the IPA in the form of a Letter of Credit. Please refer to Article V of the RFP Rules.
Why is a 17% capacity factor used for solar (fixed mount) to calculate the expected REC production? Why isn’t 100% used?
The capacity factor is used to convert the size of the system in MW to the expected REC production. The capacity factor would only be 100% if a system were to produce at full capacity in every hour of the year.
Will the Procurement Administrator consider late proposals to the DG RFP?
No. No late proposals are considered for the DG RFP.
Is the original executed Letter of Credit due at the IPA’s office by 12PM (noon) CPT on Wednesday, October 4, 2017?
Yes. A requirement of the Part 2 Proposal, which is due by noon (central) on Wednesday, October 4, 2017 (except for your bids), is to provide an original executed Letter of Credit in an amount sufficient to support your Bids. If the Letter of Credit is not received by that time, your Part 2 Proposal will be automatically deficient. You will receive a deficiency notice from the Procurement Administrator that will include a deadline for curing such deficiency. If such notice is your first deficiency notice regarding your Part 2 Proposal, you will have generally two (2) business days to provide the Letter of Credit. Additional deficiency notices generally provide less time for providing additional information or curing deficiencies.
If a Bidder has no Bids that are approved by the Commission, when will the Letter of Credit be released?
If a Bidder has no Bids that are approved by the Commission, the Letter of Credit will be cancelled as soon as practicable after the Commission decision on the results of the procurement event. The ICC is expected to decide whether to accept or reject the results of the procurement event within four (4) business days of the Bid Date. This response assumes that that Bidder is providing a new Letter of Credit for purposes of this procurement event and not an amendment to a Letter of Credit currently held by the IPA.
If a Bidder chooses not to bid all of the systems that were qualified through its Part 1 Proposal, is the Bidder still required to provide a Letter of Credit for the full amount in the notification from the Procurement Administrator?
No. The Letter of Credit must be at least in an amount equal to $4 times the number of RECs that the Bidder can win across all systems and the total Forecast Quantity across all delivery years under the applicable supplier contracts. The Letter of Credit does not need to be in an amount sufficient to support all of the RECs from the systems qualified in the Part 1 Proposal, but it must support at least 1 MW worth of RECs.
If only some and not all of the Bidder’s Bids are identified as winning Bids, does the Letter of Credit stay in place as it is or is the Bidder required to provide a new Letter of Credit to reflect the number of RECs in the winning Bids?
If a Bidder has Bids that are identified as winning Bids, the Letter of Credit issued during the Part 2 Window stays in place at the start of the supply period to the extent that some of the systems presented in the Proposal have not begun accumulating metered deliveries or to the extent that the Bidder has a winning bid on a Forecast Quantity so that some systems in the Small Size Class have not yet been identified. After the Bidder pays the Supplier Fees, the Letter of Credit will be reduced on a prorated basis based upon the number of RECs in the winning Bids as soon as practicable. During the supply period, at the end of each quarter, the Letter of Credit is further reduced as systems demonstrate that they have accumulated metered deliveries of renewable energy. The Letter of Credit will be returned once its amount is reduced or drawn down to zero.
What are the consequences if one of our identified systems does not begin accumulating metered deliveries by the required deadline? Do amounts not spent because the systems failed get rolled over to the next DG procurement?
If a system that was identified does not begin accumulating deliveries by the required deadline and it is clear that the system will not be built, the Bidder will forfeit the collateral ($4 x the number of RECs associated with this system x 5 years) associated with the RECs from such system. Furthermore, the maximum quantity of RECs that can be delivered under the contract will be reduced by the quantity of RECs associated with the project and the project will be removed from the contract.
The details of how budgets for future DG procurement event will be set are not yet available. Please note that under the terms of the contract, if a system does not begin accumulating metered deliveries by the required deadline, an extension may be granted at the IPA’s sole discretion for limited circumstances such as demonstrated delays in a utility approving interconnection of a system, or failure by the PJM EIS GATS or M-RETS to process registration in a timely manner.
Is the data provided by the Procurement Administrator and posted to the procurement website the only data available regarding the results of the DG procurement events?
The data provided by the Procurement Administrator is the only data available regarding the results of the Spring DG procurement event.
What happens if a Bidder wins several Forecast Quantities at different prices?
Under the applicable supplier contract with a given utility, there is a single blended price for each Size Class, which is calculated as the weighted average of the winning bid prices of the RECs that have been selected for award under the RFP process for that contract. As you identify systems from your Forecast Quantities, the RECs associated with such systems become eligible for delivery under the applicable supplier contract.
If there are deficiencies to the Letter of Credit, is it sufficient to provide an electronic copy of the amendment?
An original hardcopy of the executed amendment is required. The amendment should be sent via overnight delivery service to the same address where the original Letter of Credit was sent. We appreciate but do not require that you provide a tracking number by email to Illinois-RFP@nera.com.
When are the supplier fees due? Is the supplier fee related to the Letter of Credit in some way? Is the supplier fee different for RECs from identified systems versus RECs from forecast quantities?
The Letter of Credit is unrelated to the supplier fees. If the ICC approves some or all of the Bidder’s Bids, the Bidder will have seven (7) business days after ICC approval to pay to the IPA the Supplier Fees associated with those winning Bids. The ICC decision is expected on Thursday, October 19, 2017.
The Supplier Fee for the Fall 2017 DG RFP is $7 per REC for the quantity of RECs associated with winning Bids across all Delivery Years. The Supplier Fee of $7 per REC is applicable to RECs associated with identified systems and forecast quantities.
Where can I find the final budgets from the Spring 2017 DG RFP?
The final budgets for the Spring 2017 DG RFP are available on the Announcements Page of the procurement website here:
https://www.ipa-energyrfp.com/2017/04/25/dg-rfp-announcement-final-spring-budgets-for-dg-rfp/
Can you please provide an example of the calculation of the payments to the supplier under the applicable supplier contracts, the amount of the Letter of Credit, and the amount paid by the supplier for the Supplier Fees? Please assume, strictly for purposes of this example: (i) a 250 kW solar system producing 372 RECs each and every year; and (ii) a bid price of $200.
The payment for the RECs under contract would be 372 RECs/year * $200/REC * 5 years = $372,000. The amount of the Letter of Credit would be 372 RECs/ year * $4/REC * 5 years = $7,440. The amount of the Supplier Fees would be 372 RECs/year * $7/REC * 5 years = $13,020.