2026 Summer Indexed Wind, Solar, Brownfield, and Hydropower REC RFP (AIC, ComEd, and MEC)
Public Act 102-0662 (the “Climate and Equitable Jobs Act”) was signed into law and became effective on September 15, 2021. Public Act 103-0380, related to the procurement of RECs from certain hydropower projects, was signed into law and became effective on January 1, 2024. On October 20, 2025, the IPA filed its Long-Term Renewable Resources Procurement Plan (“2026 Long-Term Plan”) with the Illinois Commerce Commission (“ICC”) and the ICC issued a Final Order approving the 2026 Long-Term Plan with modifications on February 17, 2026.
A procurement for indexed renewable energy credits (“Indexed RECs”) from new utility-scale wind projects (projects over 5 MW), new utility-scale solar projects (projects over 5 MW), new brownfield site photovoltaic projects, and new hydropower projects at an existing dam or modernized or retooled hydropower projects at an existing dam was held on June 17, 2026.
The quantities to be procured were 2,500,000 RECs delivered annually from either new utility-scale wind or hydropower projects, 1,300,000 RECs delivered annually from new utility-scale solar projects, and 266,271 RECs delivered annually from new brownfield site photovoltaic projects. The Targets for this procurement event were the sum of the procurement targets for Summer 2026 from Table 5-5 of the 2026 Long-Term Plan and unfilled quantities from the prior procurement event conducted under the 2024 Long-Term Plan.
Summer 2026 Indexed REC RFP Calendar (March 26, 2026)
Announcements – Summer 2026 Indexed REC RFP
Click here to view Indexed Wind, Solar, Brownfield, and Hydropower FAQs.
Summer 2026 Indexed Renewable Energy Credit RFP Results
- Indexed REC RFP Results (June 24, 2026)
- ICC Public Notice of Indexed Renewable Energy Credit Procurement Results (June 24, 2026)
FINAL Summer 2026 Indexed REC RFP Bidder Information Webcast
- Bidder Information Webcast Presentation (April 6, 2026)
- Bidder Information Webcast Recording (April 6, 2026)
FINAL Summer 2026 Indexed REC Contract Documents
- Final Indexed REC Contract (April 6, 2026)
- Form of Guaranty
-
- Form of Letter of Credit
- Form of Surety Bond
- Example of Delivery Year Requirement Calculation for Utility-Scale Solar and Brownfield Site Photovoltaic Project (April 15, 2026)
Redline Comparisons
- Redline (Final Indexed REC Contract vs Draft Indexed REC Contract) (April 6, 2026)
- Redline (Summer 2026 Final Indexed REC Contract vs Fall 2025 Final Indexed REC Contract) (April 6, 2026)
FINAL Summer 2026 Indexed REC RFP Documents
- Final Indexed REC RFP Rules (April 6, 2026)
- Appendix 2: Illustrative Part 1 Form (April 6, 2026)
- Part 1 Form: P1 Inserts Utility-Scale Wind Projects (April 6, 2026)
- Part 1 Form: P1 Inserts Utility-Scale Solar Projects (April 6, 2026)
- Part 1 Form: P1 Inserts Brownfield Site Photovoltaic Projects (April 6, 2026)
- Part 1 Form: P1 Inserts Hydropower Projects (April 6, 2026)
- Part 1 Processing (April 6, 2026)
- Appendix 3: Illustrative Part 2 Form (April 6, 2026)
- Part 2 Form: P2 Inserts Utility-Scale Wind Projects (April 6, 2026)
- Part 2 Form: P2 Inserts Utility-Scale Solar Projects (April 6, 2026)
- Part 2 Form: P2 Inserts Brownfield Site Photovoltaic Projects (April 6, 2026)
- Part 2 Form: P2 Inserts Hydropower Projects (April 6, 2026)
- Part 2 Processing (April 6, 2026)
- Appendix 4: Minimum Requirements for Letter of Intent or Memorandum of Understanding (April 6, 2026)
- Appendices 5-7: Standard Pre-Bid Letters of Credit – ELECTRONIC VERSIONS (April 6, 2026)
- Appendices 8-10: Standard Pre-Bid Letters of Credit – HARDCOPY VERSIONS (April 6, 2026)
- Appendix 11: Illustrative Bid Form (April 6, 2026)
- Appendix 12: Confidentiality Statement (April 6, 2026)
- Appendix 13: Sample Requests for Return of Cash (April 6, 2026)
- Appendix 14: Minimum Requirements for Letter of Intent or Evidence of Employment related to Equity Level commitment (April 6, 2026)
- Appendix 15: Evaluation Process (April 29, 2026)
- Appendix 16: Energy Transition Community Grant Areas and Hydropower Preference Communities (April 17, 2026)
Digital Signature Instructions
Comment Process on Credit Instruments
- Comment Process Overview (March 16, 2026)
- Comment Process Webcast Slides (March 24, 2026)
- Comment Process Webcast Recording (March 24, 2026)
Comment Process on Benchmark Categories of Inputs, Assumptions and Data Sources
Comment Process on Draft Indexed REC Contract, Draft Preliminary Proposal Requirements
DRAFT Summer 2026 Indexed REC Contract
- Draft Indexed REC Contract (March 5, 2026)
- Section 6.1 of the Draft Indexed REC Contract (REVISED) (March 24, 2026)
- Redline Comparison
- Draft Form of Surety Bond
Draft Preliminary Proposal Requirements
Summer 2026 Indexed Wind, Solar, Brownfield, and Hydropower FAQs
- The Project is not placed in service by the end of the fourth calendar year after the calendar year in which construction began due to delays in finalizing interconnection agreements or obtaining necessary governmental permits and approvals;
- As a result of those delays, the federal Investment Tax Credit (ITC), Production Tax Credit (PTC), or Clean Electricity Investment Credit applicable to the Project is eliminated, materially reduced, or otherwise unavailable; and
- The delays are not primarily attributable to the Seller (for example, they are not the result of the Seller's failure to timely pursue permits, interconnection requests, required information submissions, or required payments).
Any termination request must be submitted in writing to the Buyer and the IPA by January 31, 2031 and must include reasonable documentation demonstrating that the Project would have qualified for the applicable federal tax credit but for the qualifying delay. The request is subject to IPA approval. If approved, the Agreement will be terminated, the Seller's Performance Assurance will be returned.
06-16-2026Under subsection 2.4(c), after multiple extensions to the Initial REC Delivery Deadline have been granted and the cause(s) of delay(s) outside the Seller’s control will not be resolved by May 31, 2035, then Seller may request termination of the agreement and return of its Performance Assurance, subject to IPA’s approval.
Whether any particular governmental action, inaction, permitting delay, or other circumstance satisfies the requirements of the Agreement would depend on the specific facts and documentation presented at the time of any request and would be evaluated by the IPA in accordance with the applicable contractual provisions.
06-16-2026Please use the Bid Form distributed with the Part 1 Notification on May 14, 2026 to submit your Bid(s) on the Bid Date on June 17. You must leave the cells in the row(s) corresponding to the Bid for the Project(s) for which you did not submit a Part 2 Proposal blank.
06-12-2026Section 2.7 is intended to function like a rate-lock or index-lock mechanism. Seller provides notice of the expected Financial Closing Date or NTP Issuance Date, the Adjustment Reference Date is set as 15 days before that expected milestone, and the IPA then endeavors to issue the adjusted Strike Price five (5) Business Days before the expected Financial Closing Date/NTP Issuance Date. Both Buyer and Seller are then required to update the Product Order of the Indexed REC Contract with the adjusted Strike Price within three (3) Business Days of IPA’s notice. This sequencing is intended to benefit Seller as it enters financial close by allowing the adjusted Strike Price to be reflected in an updated, binding Product Order that Seller and its financing entities may rely on as part of the closing formalities.
Please also review FAQ-Indexed REC-124.
06-10-2026Pursuant to Section 2.7(b) of the Indexed REC Contract, Seller will provide a written notice of an expected Financial Closing Date or NTP Issuance Date along with supporting documentation as soon as practicable for calculating the adjusted Strike Price. This notice shall be provided to Buyer and the IPA on or prior to the actual Financial Closing Date or NTP Issuance Date, as applicable. If the notice is not made by the actual Financial Closing Date or NTP Issuance Date, the IPA will designate an Adjustment Reference Date. Please note that once Seller provides this notice of an expected Financial Closing Date or NTP Issuance Date, the Adjustment Reference Date will be set and will not be amended further regardless of the actual Financial Closing Date or NTP Issuance Date.
06-03-2026In order to establish a new Officer of the Seller, please provide the name and contact information (title, address, mobile and business phone number, email address) of the new individual. This individual must be an officer, a director, or an individual otherwise empowered to undertake contracts and bind the Seller.
Additionally, you will be required to provide all applicable Part 1 Inserts duly completed and signed by the new Officer of the Seller.
05-28-2026Section 11.1 is to address the situation when Government Action adversely affects the eligibility of the Project or Product to meet the requirements of the Applicable Program or renders such Project or Product out of compliance with the Applicable Program. There are no historical examples of which the Procurement Administrator is aware. Section 11.1 simply provides a process for the Parties to take should such Government Action occur.
05-22-2026Please also refer to Section 5.4.1 of the 2026 Long-Term Plan for more information about the cost recovery provisions described in Section 5.4 of the Indexed REC Contract.
05-22-2026A numerical example of this reduction is provided in Appendix 15 to the RFP Rules available on the Final Materials page of the procurement website.
05-18-2026The $10 billion threshold applies at the level of the Surety issuer, not a parent or other level. The Surety issuer itself is required to represent it has total assets of at least $10,000,000,000.
05-15-2026Payment of the Supplier Fees to the IPA by the Bidder or Seller will be due within seven (7) business days after Commission approval of the Bids, as stated in paragraph I.3.12 of the RFP Rules. The ICC is expected to render its decision on the results of the Summer 2026 Indexed REC procurement on Wednesday, June 24, 2026.
The invoice for the supplier fee will be sent to Bidders that have Bids approved by the ICC directly from the Illinois Power Agency after the ICC decision is released.
05-08-2026No. As stated in paragraph V.6.4 of the RFP Rules, only one Bid may be submitted for a Project.
05-07-2026The expected Date of First Operation provided within the Part 1 Proposal is not binding. Under the Indexed REC Contract, the Delivery Term may begin prior to the expected Date of First Operation within the Part 1 Proposal. As stated in the agreement, the Delivery Term starts “on the date that the first REC is issued by PJM-EIS GATS or M-RETS for the Project subsequent to the Date of First Operation of the Project as recorded by PJM-EIS GATS or M-RETS (or the Hydropower Refurbishment Completion Date if the Project is a Hydropower Project that is newly Modernized or Retooled); provided that if such first REC issued for the Project is associated with a Vintage that is earlier than July 2026, then the Delivery Term shall start on the date that the first REC is issued for the Project associated with a Vintage of July 2026, and (ii) ending on the last day of the third month after the conclusion of the Acceptable Vintage Period.”
It is also acceptable for the Delivery Term to begin after the expected Date of First Operation provided in the Part 1 Proposal. However, please note that each Project selected through this RFP with a Bid approved by the Commission must deliver at least one REC to each Company by December 31, 2030. Notwithstanding the foregoing, such deadline may be extended to May 31, 2033 if Seller meets an increased collateral requirement; and may be further extended as described in the Indexed REC Contract.
05-06-2026If in the Part 1 Proposal, the Bidder elects to identify that its Project is in an ETCGA and confirms at least 50% of the Project site is located within an ETCGA, the Bidder must provide the name of the plant(s) and/or mine(s) associated with the ETCGA(s) applicable to the Project. In the Part 1 Proposal, the Bidder must provide evidence that at least 50% of the Project site is located within the applicable ETCGA(s). Such evidence, in the Part 1 Proposal, may be a map that clearly displays the distance between the plant(s) and/or mine(s) and the Project site and includes the names of the plant(s) and/or mine(s). The Officer of the Seller must also certify that at least 50% of the Project site will be located within the boundary of the ETCGA(s) associated with the plant(s) and/or mine(s) named in the Part 1 Proposal.
For purposes of evaluating the Part 1 Proposal, the Procurement Administrator will confirm that at least 50% of the boundary line on the Project site map is within the 30-mile radius of the coordinates associated with the names of the plant(s) and/or mine(s) named in the Part 1 Proposal. If confirmed, the name(s) of the plant(s) and/or mine(s) identified in the Proposal will be an input to the Product Order in the Indexed REC Contract should the Bid for the Project be selected and approved by the Commission.
Under the Indexed REC Contract, if the Seller has committed for the Project to be located within one or more ETCGA(s) in the Proposal, the Seller must provide to each Buyer and the IPA information and documents sufficient to verify that at least 50% of the Project is located within the ETCGA(s) as identified in the Product Order within thirty (30) days of the Date of First Operation. In the event that the Seller fails to demonstrate, and the IPA is unable to verify, that at least 50% of the Project is located within the ETCGA(s) in connection with the IPA’s review of information submitted of such Project, then an Event of Default shall be deemed to have occurred and the Indexed REC Contract shall be terminated. More information regarding payments and damages in this case is available in Section 2.5(c) of the Indexed REC Contract.
For purposes of the IPA verifying that at least 50% of the Project that is ultimately built is located within the ETCGA(s), the IPA would accept a map that clearly displays the distance between the plant(s) and/or mine(s) identified in the Product Order and the Project that is built. The Project boundary in this case may be based on (1) the acres associated with the final parcels of land on which the equipment for the Project is sited; and/or (2) the subset of acres beneath the equipment for the Project. Methods (1) and (2) may be used together when developing the Project boundary. The IPA will confirm that at least 50% of the acres associated with this Project boundary is within the 30-mile radius of the coordinates associated with the names of the plant(s) and/or mine(s) in the Product Order. For avoidance of doubt, securing additional parcels of land on which the equipment does not reside so as to increase the acres within the ETCGA would not be acceptable.
05-01-2026It is acceptable for the signatures by each Signatory for each Joint Venture Partner to be completed on separate Inserts with one signature on each Insert or on a single Insert with additional signatures placed below or to the side of the signature line.
04-29-2026Please note that if there are other entities not already named in the Part 1 Proposal that are currently involved in the development of the Project, these entities must be disclosed in the Project Team Insert (#P1-2). This is a new requirement for the Summer 2026 Indexed REC RFP. Please see paragraph IV.1.6 for additional information on the Project Team.
04-29-2026Additionally, please note that you may submit a System Impact Study with certain financial terms redacted as long as the Procurement Administrator is able to verify that the document is relevant to the Project, and that any operational characteristics listed in the study, such as Project size and location, are consistent with other information provided in the Part 1 Proposal.
If the completed System Impact Study is not available, then the Bidder may provide a document that shows that the Project is further in the interconnection process such as an interconnection agreement. However, draft documents are not acceptable.
04-24-2026Please refer to paragraph IV.1.7 of the RFP Rules for additional rules governing a Joint Venture arrangement. Paragraph IV.1.7 states, “If: (i) a Partner for a Joint Venture Project (“Project 1”) is a member of the Project Team for another Project (“Project 2”); and (ii) Project 1 and Project 2 are presented by different Bidders, such Partner must advise the Procurement Administrator of this fact as soon as practicable and no later than the Part 1 Date. More generally, if an entity is a Partner in a Joint Venture with potentially multiple Projects (Projects 1a, 1b, 1c, etc., as applicable, the “Project 1s”) and such entity is also a member of the Project Team for Projects presented by another Bidder (Project 2a, 2b, 2c, etc., as applicable, the “Project 2s”), then such Partner must advise the Procurement Administrator of this fact as soon as practicable and no later than the Part 1 Date. […] In such a case, Project 1 and Project 2 must belong to different Categories. More generally, the Category or Categories of the Project 1s cannot overlap with the Category or Categories of the Project 2s. For example, Project 1s could be all Solar Projects and Project 2s could be all Wind Projects (but it could not be the case that Project 1a and Project 2b are both Solar Projects).”
In your example, given that Projects A and B belong to the same Category, it would not be acceptable for a Proposal for Project A and a Proposal for Project B to be submitted by two different Bidders given that both Proposals involve Company B. It would be acceptable for Company B (or another entity that can take the lead in preparing the Proposals for both Projects) to present the Proposals for both Project A and Project B.
04-24-202604-22-2026
The Letter of Credit for a Company may only include modifications to the Standard Pre-Bid Letter of Credit acceptable to that Company, applicable specifically to either the Electronic Version or Hardcopy Version, and posted to the procurement website. The final lists of acceptable modifications are expected to be posted to the Final Materials page on Monday, April 27, 2026.
If you are using Pre-Bid Letters of Credit to post bid assurance collateral, please have the Issuing Bank submit the final, executed version to each Company using the instructions provided. Bid assurance collateral must be received by 12 PM (noon) CPT on Wednesday, June 3, 2026 (the Part 2 Date) along with all other information and documents required by the Part 2 Proposal except for a Bidder’s Bids.
If a Bidder submits a Pre-Bid Letter of Credit for a Company, the Bidder will receive notice of whether such Pre-Bid Letter of Credit is acceptable to the Company as specified in the Part 2 Proposal Processing Procedures. Please see the Part 2 Processing document posted to the Final Materials page of the Indexed REC section of the procurement website for information on the timing of such notices.
04-22-2026Please note that Project Labor Agreement requirements are not applicable to New Hydropower Projects.
04-22-2026In addition, please refer to FAQ-Indexed REC-73.
04-20-2026The invoice for the supplier fee will be sent to Bidders that have Bids approved by the ICC directly from the Illinois Power Agency after the ICC decision is released.
04-20-2026Additionally, there is no requirement for where a Project must be interconnected or deliver its energy. The Project must either be in Illinois or in a state adjacent to Illinois. However, please note that a Project that is located in a state adjacent to Illinois must meet the public interest criteria specified in Section 1-75(c)(1)(I) of the IPA Act by submitting data about the Project to the IPA and obtaining pre-approval from the IPA that the Project is eligible for Illinois RPS compliance.
04-16-2026Please note that the public disclosure does not indicate if a Bid is an Opt-in Bid. For details about what information is publicly disclosed for winning Projects, please see FAQ-Indexed REC-43.
04-16-2026This is not possible. Under the Indexed REC Contract, the entity named as the Guarantor and that provides the Guaranty must have credit ratings directly assigned to it by Fitch, Moody’s, and/or S&P to qualify for a Collateral Threshold equal to $2,500,000.
04-16-202604-16-2026
As stated in Section 10.1 of the Indexed REC Contract, “Force Majeure may include curtailments of the Project made by the regional transmission organization or independent system operator responsible for the operation of the transmission system to which the Project is interconnected, any transmission provider providing transmission services for the Project, the utility interconnecting with the Project and providing interconnection services to the Project, or a Governmental Authority, provided that such curtailment was not initiated by the Project or Seller. Upon such Force Majeure event, the Shortfall Amount in a Delivery Year may be excused by the amount of such curtailment. Seller shall provide written notice to Buyer within thirty (30) days of the commencement of any curtailment that meets the foregoing requirements and, in the event that Seller fails to so notify Buyer, Seller shall not be relieved of its Delivery obligations as a result of such curtailment. Upon the occurrence and proper notice of a curtailment meeting the foregoing requirements, Seller shall estimate the amount of Deliveries prevented by such curtailment based on the most recent twelve (12) months of Actual Production data from the Project and utilizing actual meteorological conditions during the period of curtailment and shall provide such estimate to Buyer along with all supporting documentation, including any supporting information from the entity that curtailed the Project’s generation”.
04-16-2026First, the Procurement Administrator cannot advise bidders on their bid submissions. The Strike Price that you indicate in your Bid will be used to calculate the payments under the Indexed REC Contract and there is no separate payment adjustment related to additional battery storage under the Indexed REC Contract.
Second, with respect to a Project co-located with an energy storage facility, the RECs Delivered shall be associated with energy generated exclusively from the Project as measured by the Project’s Revenue Quality Meter and not from any other electric source. Similarly, the MWh hourly generation that must be provided under Section 6.1 of the Indexed REC Contract for which the REC Monthly Price Hourly Component is calculated must be from the Project as measured by the Project’s Revenue Quality Meter and not from any other electric source. As such, increasing the Actual Production and REC quantity (as these terms are defined in the Indexed REC Contract) by using a battery is prohibited.
04-16-2026A Company may draw upon the letter of credit or a cash deposit if: (i) the Bidder or a Seller has disclosed information relating to the Proposal for a Project publicly or to any other party (excluding disclosures required by a federal, state, or local agency, or by a court of competent jurisdiction) before the Illinois Commerce Commission has rendered its decision on the results of the procurement event; or (ii) the Bidder or a Seller has made a material omission or misrepresentation in the Part 1 Proposal or the Part 2 Proposal for a Project submitted in connection with the procurement event; or (iii) a Seller has failed to execute the applicable supplier contract for a Project within three (3) business days of being notified that the Illinois Commerce Commission has approved the Bid on that Project or has failed to meet the creditworthiness requirements of the applicable supplier contract within fifteen (15) business days of such Illinois Commerce Commission decision; or (iv) the Bidder or a Seller has failed to pay to the Illinois Power Agency the applicable Supplier Fee for a Project within seven (7) business days of being notified that the Illinois Commerce Commission has approved the Bid on that Project.
Please see FAQ-Indexed REC-82 for additional information on timing of the return of bid assurance collateral.
04-16-202604-16-2026
Please also refer to FAQ-Indexed REC-27 for information about the Collateral Requirement for Sellers not eligible for unsecured credit.
04-16-2026If the Bid for a Project is not selected by the evaluation procedure, the bid assurance collateral for that Project will be returned as stated in Paragraph VI.2.22 of the RFP Rules, “A Pre-Bid Letter of Credit will expire on the date stated as part of its terms, twenty-one (21) business days after the anticipated date of the Commission decision on the procurement event and cash provided as bid assurance collateral will be returned in the same general timeframe”. Return of cash tendered as bid assurance to a Company is not initiated until the Company receives fully executed request for return of cash in a form acceptable to the Company. AIC requires additionally that an account in AIC’s vendor portal be set up for the entity to which cash is returned. MEC requires additionally receipt of a completed Vendor Request Form that MEC finds acceptable. Please note that for a Bidder who is not yet set up on AIC’s portal used for the return of cash, account set up may take six (6) business days after the ICC’s decision on the procurement results.
Please note that Cash posted as bid assurance collateral under the RFP may be used towards meeting the performance assurance requirement under the contract. In this case, the Bidder needs only to make a second wire for the difference between the performance assurance requirement and the bid assurance collateral already posted, if the difference is positive. A Bidder indicates whether it elects for cash to be retained by the applicable Company in the Contract Insert, also labelled INSERT #P2-4, as further described in Paragraph V.3.2.
Please see paragraph V.2.2. of the Indexed REC RFP Rules for the conditions under which a draw on cash posted as bid assurance collateral may be made.
04-16-2026A Seller with a Project with an approved Bid must meet the creditworthiness requirements under the Indexed REC Contract within fifteen (15) business days of the Illinois Commerce Commission decision on the results of the procurement event. The Performance Assurance must be posted no later than July 16, 2026. It is Seller’s responsibility to ensure Seller’s Performance Assurance is maintained pursuant to Article 7 of the Indexed REC Contract. Pursuant to Section 7.1(c) of the Indexed REC Contract, at the conclusion of the Delivery Term of the Indexed REC Contract upon completion of the final delivery obligations and payment obligations under the Indexed REC Contract, Seller may request for the return of Seller’s Performance Assurance.
04-16-2026The Bid Assurance Collateral Instructions for each Company will be distributed to Bidders shortly after the Part 1 Date, which is Thursday, April 30, 2026. The instructions will include both information on how to submit cash as bid assurance collateral to the Companies as well as how to transmit the Pre-Bid Letter of Credit to the Companies, including the physical address for each of the companies.
04-16-202604-16-2026
The Supplier Fee is non-refundable.
04-16-202604-16-2026
Employees, contractors and their employees, and subcontractors and their employees, whose job duties are directly required by or substantially related to the development, construction, and operation of a project that is participating in or intended to participate in the IPA-administered programs and procurements under Section 1-75(c) of the IPA Act. This shall include both project installation workforce and workforce in administrative, sales, marketing, and technical roles where those workers’ duties are performed in Illinois. For purposes of this definition, ‘directly required by or substantially related to’ shall be construed to be any direct employee of the Approved Vendor, Designee, or Indexed REC contract holder, or any contractor and its employees whose contract exceeds 5% of the REC Contract value. Employees of contractors below that threshold may be counted toward the MES on a voluntary basis, but then all contractors below the 5% of REC contract value threshold must be included. (2026 Long-Term Plan at 404-405).
The MES applies to the project workforce, so if the MES is 14%, EEPs must make up 14% of the project workforce. Therefore, compliance with the MES is based on number of workers or employees, not the work hours performed by those employees.
04-16-2026No additional documentation or information is required at the time of Bid submission.
04-16-2026A Minimum Equity Standard of 14% will apply under the Indexed REC Contract to a Project selected through this RFP if the Date of First Operation (or the Hydropower Refurbishment Completion Date if the Project is a hydropower project that is newly Modernized or Retooled) is on or after December 15, 2022, regardless of whether the project is located in Illinois or an Adjacent State.
An “Equity Eligible Persons” means persons who would most benefit from equitable investments by the State designed to combat discrimination, specifically: (a) persons who graduate from or are current or former participants in the Clean Jobs Workforce Network Program, the Clean Energy Contractor Incubator Program, the Illinois Climate Works Pre-apprenticeship Program, Returning Residents Clean Jobs Training Program, or the Clean Energy Primes Contractor Accelerator Program, and the solar training pipeline and multi-cultural jobs program created in paragraphs (a)(1) and (a)(3) of Section 16-108.12 of the Public Utilities Act; (b) persons who are graduates of or currently enrolled in the foster care system; (c) persons who were formerly incarcerated; (d) persons whose primary residence is in an Equity Investment Eligible Community as defined in Section 1-10 of the IPA Act as further clarified in the IPA’s long term renewable resources procurement plan as approved by the Illinois Commerce Commission in ICC Docket No. 25-0945.
As defined in the Indexed REC Contract, “Project Workforce” means employees, contractors and their employees, and subcontractors and their employees whose job duties are directly required by or substantially related to the development, construction, and operation of the Project that is participating in the IPA-administered programs and procurements under Section 1-75(c) of the IPA Act. This shall include both project installation workforce and workforce in administrative, sales, marketing, and technical roles where those workers’ duties are directly related to the Project. For workforce in administrative, sales, marketing and technical roles, this shall apply only if those workers are located in Illinois. For purposes of this definition, “directly required by or substantially related to” shall be construed to be any direct employee of Seller, or any contractor and its employees whose contract exceeds 5% of the REC Contract Value. Employees of contractors below that threshold may be counted toward the MES on a voluntary basis, but then all employees of all contractors below the 5% of REC Contract Value threshold must be included.
Persons working in administrative, sales, marketing and technical roles, shall be included in the Project Workforce only if their duties are related to the Project and performed in Illinois. The project installation workforce shall be included in the Project Workforce and must meet the MES regardless of location.
Please note, CEJA provides that the Agency may utilize its discretion in rare circumstances to grant a waiver of the MES (20 ILCS 3855/1-75(c-10)(4)(E)). In describing the criteria for granting such a waiver, the statute provides that the Agency may do so “where the applicant provides evidence of significant efforts toward meeting the minimum equity commitment, including: use of the Energy Workforce Equity Database; efforts to hire or contract with entities that hire eligible persons; and efforts to establish contracting relationships with eligible contractors.” (20 ILCS 3855/1-75(c-10)(4)(E) (emphasis added)). The IPA posted waiver request forms to the Minimum Equity Standard webpage here: https://ipa.illinois.gov/diversity-equity-and-inclusion/minimum-equity-standard.html. As described in the waiver request form, requestors must receive at least 20 points to qualify for a waiver.
04-16-2026The Company may draw upon the letter of credit or a Company may draw upon a cash deposit if: (i) the Bidder or a Seller has disclosed information relating to the Proposal for a Project publicly or to any other party (excluding disclosures required by a federal, state, or local agency, or by a court of competent jurisdiction) before the Illinois Commerce Commission has rendered its decision on the results of the procurement event; or (ii) the Bidder or a Seller has made a material omission or misrepresentation in the Part 1 Proposal or the Part 2 Proposal for a Project submitted in connection with the procurement event; or (iii) a Seller has failed to execute the applicable supplier contract for a Project within three (3) business days of being notified that the Illinois Commerce Commission has approved the Bid on that Project or has failed to meet the creditworthiness requirements of the applicable supplier contract within fifteen (15) business days of such Illinois Commerce Commission decision; or (iv) the Bidder or a Seller has failed to pay to the Illinois Power Agency the applicable Supplier Fee for a Project within seven (7) business days of being notified that the Illinois Commerce Commission has approved the Bid on that Project.
04-16-2026Under the Indexed REC Contract, Collateral Requirement means, (a) with respect to a Utility-Scale Wind Project or a Hydropower Project, an amount equal to four dollars ($4) times the Annual Quantity and which shall be reduced for the last Delivery Year, if applicable, to reflect an amount equal to the product of the Delivery Year Requirement for the last Delivery Year and four dollars ($4); provided that if the Collateral Requirement is calculated to be less than $20,000, then the Collateral Requirement shall be $20,000; and means, (b) with respect to a Utility-Scale Solar Project or a Brownfield Site Photovoltaic Project, an amount equal to ten dollars ($10) times the Annual Quantity and which shall be reduced for the last Delivery Year, if applicable, to reflect an amount equal to the product of the Delivery Year Requirement for the last Delivery Year and ten dollars ($10); provided that if the Collateral Requirement is calculated to be less than $20,000, then the Collateral Requirement shall be $20,000.
The Increased Collateral Requirement means, (a) with respect to a Utility-Scale Wind Project or a Hydropower Project, an amount equal to eight dollars ($8) times the Annual Quantity; provided that if the Increased Collateral Requirement is calculated to be less than $40,000, then the Increased Collateral Requirement shall be $40,000; and means, (b) with respect to a Utility-Scale Solar Project or a Brownfield Site Photovoltaic Project, an amount equal to twenty dollars ($20) times the Annual Quantity; provided that if the Increased Collateral Requirement is calculated to be less than $40,000, then the Increased Collateral Requirement shall be $40,000. The Increased Collateral Requirement shall revert to the Collateral Requirement upon Delivery of one (1) REC from the Project by Seller by the extended Initial REC Delivery Deadline.
04-16-202604-16-2026
No, all RECs delivered to the Buyer must be from the Project selected under the RFP. As stated in Section 4.1(a) of the Indexed REC Contract, “All RECs Delivered to Buyer from Seller under this Agreement shall be associated with electric energy generated by the Project.”
04-16-2026Seller shall Deliver RECs to Buyer to satisfy the Delivery Year Requirement in each Delivery Year (June – May). Delivery Year Requirement is defined in Section 1.33 of the Indexed REC Contract. RECs generated by the Project in excess of the Delivery Year Requirement for any Delivery Year are deemed Excess RECs; the amount of RECs that Seller fails to Deliver to satisfy the Delivery Year Requirement for a Delivery Year is deemed the Shortfall Amount. It is an event of default if (i) Seller fails to meet the Delivery Year Requirement for five (5) or more years, and (ii) the Shortfall Amounts (as the term is defined in the Indexed REC Contract) cumulatively equals or exceeds 3.5 times the Annual Quantity.
Excess RECs:
- If the Delivery Year Requirement is already met, then any RECs generated by the Project in excess of the Delivery Year Requirement for any Delivery Year are deemed Excess RECs. Such Excess RECs shall remain the exclusive property of Seller, to be utilized in Seller’s sole discretion. For avoidance of doubt, such Excess RECs are not eligible for payment by Buyer except as provided in Section 2.3(f)(ii). In the event that the Delivery Year Requirement for a Delivery Year has been met and Excess RECs are Delivered to Buyer such Excess RECs shall be disposed pursuant to Section 2.3(f).
- Excess RECs may be used for purposes of reducing Shortfall Amounts. Please review Section 4.1(k) of the Indexed REC Contract for more information.
Shortfall Amounts:
- In the event that Seller fails to Deliver the Delivery Year Requirement for a Delivery Year, the amount of RECs that Seller fails to Deliver to satisfy the Delivery Year Requirement for a Delivery Year shall be deemed the “Shortfall Amount”. Please review Section 4.1(f) of the Indexed REC Contract for more information.
- Regarding flexibilities related to Shortfall Amounts, please see FAQ-Indexed-REC-64.
- The Annual Quantity in the Indexed REC Contract related to a utility-scale solar project or a brownfield site photovoltaic project is subject to a degradation factor that is calculated using the Degradation Rate designated by the Bidder within the Part 2 Proposal. The Delivery Year Requirement calculation is set forth in Section 1.32 and 1.33 of the Indexed REC Contract.
- Seller must deliver a quantity of RECs that meets the Delivery Year Requirement in each deliver year, the failure to meet any Delivery Year Requirement through the first two (2) full Delivery Years (i.e., first two (2) full June through May periods as well as any prior stub period) shall not constitute a Shortfall Amount.
- As described in Section 9.2 it is an event of default under the Indexed REC Contract if: (i) Seller fails to meet the Delivery Year Requirement for five (5) or more years, and (ii) the Shortfall Amounts (as the term is defined in the Indexed REC Contract) cumulatively equals or exceeds 3.5 times the annual quantity.
- Section 9.2(k) outlines the process for a Seller to request a waiver excusing Shortfall Amounts or a portion of such Shortfall Amounts from the IPA. Approval of waivers to Shortfall Amounts may be granted by the IPA on a case-by-case basis upon a demonstration of good cause by Seller to the satisfaction of the IPA at its sole discretion. Good cause may include long-term changes in weather patterns, serial defects in the Project’s components, and other events outside of the control of Seller that impact the Project’s ability to meet its Delivery Year Requirement. The approval of any such requests shall be at the IPA’s sole discretion.
- There is flexibility on Project size changes after contract award subject to the terms of the Indexed REC Contract.
- There is an option for Seller to indicate a percent of the project’s output it elects to commit to the Buyer under the applicable Indexed REC contract so as to allow for a third party off-taker to procure a portion of the project’s output that is not committed to the Buyer under the applicable the Indexed REC contract. Please review Section 2.3(b) of the Indexed REC Contract for information regarding the Project Committed Percentage and the Standing Order.
- A process for Seller to make manual transfer of RECs to the Buyer(s) for the purpose of reducing Shortfall Amounts incurred in one or more Delivery Years, which may include RECs that were generated in excess of prior Delivery Year Requirements and RECs that were not previously committed to the Buyer(s). Please review Section 4.1(k) of the Indexed REC Contract for information regarding the manual transfer of RECs for purposes of reducing Shortfall Amounts.
04-16-2026
- the Queue/OASIS ID from PJM and a copy of the completed System Impact Study from PJM for the Project; or
- the Project Number from MISO and a copy of the Preliminary System Impact Study under Definitive Planning Phase 1 (“DPP 1”) under the DPP-2020-Cycle 1 or a later study cycle; or
- the Project Number from MISO and a copy of the fully executed interconnection agreement for the Project; or
- a fully executed interconnection agreement with a utility for the Project.
If none of the information bulleted above is available for the Project, or if the Bidder cannot provide a document that shows that the Project is further in the interconnection process, then the Bidder must: (i) if available, provide the Queue/OASIS ID from PJM, the Project Number from MISO, or the applicable ID/Number associated with the Project under the interconnection process with a utility; (ii) describe the stage of development of the Project applicable to the point of interconnection (including providing the name of the regional transmission organization or utility with which the Project plans to interconnect; e.g., PJM, Ameren, etc.) and to the size of the Project; and (iii) demonstrate control for a portion of the Project site as described in Paragraph IV.6.3.
According to Paragraph IV.6.3 of the RFP Rules, a “A Bidder that demonstrates site control to meet the requirements of Section IV.6, must do so for a portion of the Project site that covers an area of at least 40 acres times the Project size for a utility-scale wind project, an area of at least 4 acres times the Project size for a utility-scale solar project, or an area of at least 3 acres times the Project size for a brownfield site photovoltaic project. For example, if the Project size for a utility-scale wind project is 10 MW, then the Bidder must demonstrate control for 400 acres included in the Project site.”
04-16-2026There is no requirement to utilize Equity Eligible Contractors (EECs) to meet the Minimum Equity Standard. As defined in the Indexed REC Contract, “Minimum Equity Standard” means specific requirements provided in Section 1-75(c-10) of the IPA Act, for which a minimum percentage of the Project Workforce must consist of Equity Eligible Persons or Equity Eligible Contractors”.
04-16-2026If a Bidder submits Proposals for multiple Projects, but ultimately decides not to present a Part 2 Proposal for all of the Projects that qualified through a successful Part 1 Proposal, such Bidder should notify the Procurement Administrator by email at Illinois-RFP@nera.com, with the list of Projects for which the Bidder will not be submitting a Part 2 Proposal as early as practicable and no later than the Part 2 Date. The Procurement Administrator will refer to this list of Projects submitted by the Bidder in conjunction with the Part 2 Proposals submitted in order to determine if the Bidder has provided sufficient bid assurance collateral to all Companies.
For the Bidder to be able to submit a Bid on a Project, the Bidder must have submitted bid assurance collateral to all Companies in an amount that is sufficient given the Project size. In the case where a Bidder submits Proposals for multiple Projects and elects to effect a wire transfer to each Company or to submit a Pre-Bid Letter of Credit to each Company that covers two (2) or more of the Bidder’s Projects, then if the Bidder fails to provide bid assurance collateral to one or more of the Companies, or if the amount of the bid assurance collateral for one or more of the Companies is insufficient for all such Projects, then the Part 2 Proposals for all such Projects will be considered deficient.
04-16-2026- The amount of bid assurance collateral required for AIC is $1,600/MW for a Wind Project and Hydropower Project and $5,500/MW for a Solar Project and Brownfield Project.
- The amount of bid assurance collateral required for ComEd is $4,000/MW for a Wind Project and Hydropower Project and $13,000/MW for a Solar Project and Brownfield Project.
- The amount of bid assurance collateral required for MEC is $400/MW for a Wind Project and Hydropower Project and $1,000/MW for a Solar Project and Brownfield Project.
There is no cap on the amount of bid assurance collateral tendered to each utility.
For the Bidder to be able to submit a Bid on a Project, the Bidder must have submitted bid assurance collateral to all Companies in an amount that is sufficient given the Project size. In the case where a Bidder submits Proposals for multiple Projects and elects to effect a wire transfer to each Company or to submit a Pre-Bid Letter of Credit to each Company that covers two (2) or more of the Bidder’s Projects, then if the Bidder fails to provide bid assurance collateral to one or more of the Companies, or if the amount of the bid assurance collateral for one or more of the Companies is insufficient for all such Projects, then the Part 2 Proposals for all such Projects will be considered deficient
04-16-202604-16-2026
As stated in Section 2.5.2.4 of the IPA’s 2026 Long-Term Renewable Resources Procurement Plan, “The Illinois Commerce Commission has adopted administrative rules for the certification of utility-scale [solar] and distributed generation installers under Section 16-128A of the PUA. The Commission has specifically defined the terms “qualified person” and “install” for both categories of projects. Any entity seeking to develop new photovoltaic projects in Illinois should be aware of the Commission’s Part 461 rules (governing installers of utility-scale photovoltaics), Part 468 rules (governing distributed generation installers) and the certification process more generally.” The Illinois Commerce Commission has regulatory authority over solar installers in Illinois; questions related to the interpretation of the Commission’s administrative rules are best directed to the Commission.
For utility-scale solar projects, the definitions of “install” and “qualified person” for project installations, and details for utility-scale solar installer certification under Section 16-128A of the PUA (220 ILCS 5/16-128A) and 83 Ill. Adm. Code 461 (“Part 461”) are accessible here.
For distributed generation facilities, the definitions of “install” and “qualified person” for project installations, and details for distributed generation facilities installer certification under Section 16-128A of the PUA and 83 Ill. Adm. Code 468 (“Part 468”) are accessible here.
04-16-2026The Equity Accountability System is the umbrella suite of policy levers and standards included in the Illinois Power Agency Act that advance “priority access to the clean energy economy for businesses and workers from communities that have been excluded from economic opportunities in the energy sector, have been subject to disproportionate levels of pollution, and have disproportionately experienced negative public health outcomes” (20 ILCS 3855/1-75(c-10)). The Equity Accountability System includes the Minimum Equity Standard (“MES”), the reserved category in the Adjustable Block Program for Equity Eligible Contractors (“EECs”), and the requirements developed by the Agency to ensure “that competitive procurement processes, including utility-scale solar, utility-scale wind, and brownfield site photovoltaic projects, advance the equity goals” of the Climate and Equitable Jobs Act (20 ILCS 3855/1-75(c-10(3))).
The IPA, through its 2026 Long-Term Renewable Resources Procurement Plan (“Long-Term Plan” or “Plan”), requires utility-scale projects bidding into competitive procurements for Indexed REC contracts to meet the MES and provides additional prioritization for projects that employ a higher percentage of Equity Eligible Persons (“EEPs”) than that required by the MES. Thus, the MES and the equity prioritization mechanism constitute the pieces of the Equity Accountability System applicable to bidders in competitive procurements, and those steps constitute full compliance with the Equity Accountability System.
The IPA created a Minimum Equity Standard (MES) webpage to provide the most up to date MES related documents, educational resources, and training materials related to MES Compliance Plans and waiver requests. Please visit the IPA Minimum Equity Standard webpage here: https://ipa.illinois.gov/diversity-equity-and-inclusion/minimum-equity-standard.html
In particular, the IPA posted an MES Compliance and Waiver Request Training Presentation applicable to utility-scale solar and wind projects under the header “MES Educational Resources”.
04-16-2026- Persons who graduate from or are current or former participants in the Clean Jobs Workforce Network Program, the Clean Energy Contractor Incubator Program, the Illinois Climate Works Pre-apprenticeship Program, the Returning Residents Clean Jobs Training Program, or the Clean Energy Primes Contractor Accelerator Program, and the solar training pipeline and multi-cultural jobs program created in paragraphs (a)(1) and (a)(3) of Section 16-108.21 of the Public Utilities Act;
- Persons who are graduates of or currently enrolled in the foster care system;
- Persons who were formerly incarcerated; [or]
- Persons whose primary residence is in an equity investment eligible community. (20 ILCS 3855/1-10).
A person may fall into multiple categories or only one; a person does not need to have participated in a CEJA- or FEJA-funded training program in order to be an EEP if they qualify under one of the other categories.
An “equity investment eligible community” is defined by CEJA as:
- R3 Areas as established pursuant to Section 10-40 of the Cannabis Regulation and Tax Act, where residents have historically been excluded from economic opportunities, including opportunities in the energy sector; and
- Environmental justice communities, as defined by the Illinois Power Agency pursuant to the Illinois Power Agency Act, where residents have historically been subject to disproportionate burdens of pollution, including pollution from the energy sector. (20 ILCS 3855/1-10).
A map of R3 Areas can be found here, a map of environmental justice communities can be found here, and the Equity Investment Eligible Community Map that combines EJ and R3 areas can be found here.
04-16-2026At the start of each delivery year, the Agency shall require a compliance plan from each entity participating in a procurement program of subsection (c) of this Section [1-75] that demonstrates how they will achieve compliance with the minimum equity standard percentage for work completed in that delivery year. (20 ILCS 3855/1-75(c-10)(1)(A)).
Competitive procurements are required by Section 1-75, and therefore applicants to those procurements must submit a Compliance Plan under the law.
The Compliance Plan is meant to ensure that applicants are making a concerted effort to hire EEPs and contribute to the equity goals of CEJA. The law requires participants to complete a Compliance Plan, which contains the elements outlined above, and directs the Agency to ensure that competitive procurements advance the equity goals of CEJA. As laid out by the statute, CEJA envisions the EAS as a method to create “priority access to the clean energy economy for businesses and workers from communities that have been excluded from economic opportunities in the energy sector, have been subject to disproportionate levels of pollution, and have disproportionately experienced negative public health outcomes.” (20 ILCS 3855/1-75(c)(10)). Accounting for generations of such exclusion and disproportionate harms requires buy-in from all stakeholders and coordination between the public sector and private sector actors. The IPA hopes that all participants in competitive procurements take this policy seriously and contribute sincere efforts to creating a more equitable clean energy economy in Illinois.
04-16-2026[The] Bidder must provide a narrative plan to meet the Equity Level (%) provided in the Part 1 Proposal. The narrative plan must include the following items:
- a narrative description of how the Seller will ensure that at least the Equity Level (%) will be met;
- a statement of intent to comply with all necessary requirements set forth in Public Act 102-0662 relating to the Minimum Equity Standard and agreement to comply with certain obligations, including hiring a diverse project workforce and working with Equity Eligible Contractors, where applicable;
- the total projected number of workers related to Construction Activities up to the point of the Date of First Operation, or up to the Hydropower Refurbishment Completion Date if the Project is a Modernized or Retooled Hydropower Project;
- plans for the use of Equity Eligible Contractors, if applicable;
- Seller classification (i.e., Minority-owned business enterprise, Woman-owned business enterprise, Disabled-owned business, Veteran-owned business, Small business, etc.), if applicable;
- the qualifying Equity Eligible Person category/categories the Seller seeks to hire, if known; and
- a communication plan for local outreach to increase the utilization of Equity Eligible Persons and Equity Eligible Contractors.
Many of these elements may be repeated in the eventual Compliance Plan submitted after a contract has been awarded to a selected bid. Given that the strike price for a project that submits an Equity Level (%) greater than the Minimum Equity Standard of 14% will be reduced for purposes of bid ranking, additional assurances should be provided that the Bidder will meet this commitment.
04-16-2026CEJA directs the IPA to develop an Energy Workforce Portal in consultation with the Department of Commerce and Economic Development that consists of a searchable database of vendors, suppliers, and contractors that are minority and women-owned business enterprise certified or are certified as EECs. The IPA’s Energy Workforce Equity Portal is designed to help connect clean energy companies with Equity Eligible Persons looking to work in the clean energy sector in Illinois. Developers of clean energy projects, such as developers of utility-scale wind, utility-scale solar, and brownfield site solar projects, can use this portal to advertise clean energy jobs and to search for Equity Eligible Persons seeking employment, as Equity Eligible Persons register on the portal. Developers can also use the portal to apply to qualify as an Equity Eligible Contractor. Please visit the IPA Energy Workforce Equity Portal here.
Phase I of the portal was launched on January 31, 2023 and includes:
- Information on qualifications and requirements for job seekers to become Equity Eligible Persons.
- A form for applying to be certified as Equity Eligible Person.
- A listing of Equity Eligible Persons who have volunteered to identify themselves to potential clean energy companies.
- Information on job postings from clean energy companies for which they are recruiting Equity Eligible Persons.
- Information on workforce training programs administered by DCEO.
- Equity Investment Eligible (EIE) Community Map that can be utilized by anyone to determine if they or someone else reside in an identified equity investment eligible community.
- Information on Equity Eligible Contractors participating in the IPA’s Adjustable Block Program.
- FAQs outlining commonly asked questions and answers on the portal.
- A user guide to help clean energy companies and Equity Eligible Persons navigate the portal easily.
Phase II of the Portal, launched in Summer 2023, includes enhancements to help facilitate more inclusive participation in the clean energy workforce. Additional information can be found on the Portal’s Resources page.
The IPA hosted a training for participants to get acquainted with the portal and its various functionalities. This includes advertising jobs and searching for Equity Eligible Persons seeking employment, as they register on the portal. The training is available here.
The Energy Workforce Equity Database should serve as a tool for applicants to find EEPs, but may not include the entire universe of available EEPs seeking clean energy work, since it will only list EEPs that voluntarily add their information to the database. The Database is still in development and applicants should not assume they will be able to rely solely on the Database to find EEPs to meet the Minimum Equity Standard.
04-16-2026Please monitor the DCEO CEJA website for updates from the Department on its job training programs.
04-16-2026The IPA encourages applicants to utilize all possible means for identifying, recruiting, and hiring EEPs, especially those that qualify by virtue of their status as formerly incarcerated, a graduate of the foster care system, or a resident of an equity investment eligible community. The Long-Term Plan outlined several strategies that may be useful:
- Working with State-approved job training and workforce development programs to recruit EEPs and provide evidence of outreach
- Maintaining applications of individuals not selected for an opening for contact regarding future project openings
- Participating in job fairs and related local community events to recruit a diverse workforce
- Continuing utilization the Energy Workforce Equity Portal
- Outreach on various platforms of targeted social media, engagement in direct outreach to relevant associations or organizations to notify them of the project opportunity. (2026 Long-Term Plan at page 410).
The IPA cannot provide advice to bidders regarding the specifics of a recruitment strategy or point an entity toward specific organizations or events where it might recruit EEPs.
04-16-2026Under Section 6.4 of the Indexed REC Contract, to demonstrate compliance with the MES the following reports must be submitted to the IPA , if applicable pursuant to Section 6.4(a) of the Indexed REC Contract;
- First MES Compliance Plan. The first MES Compliance Plan shall be submitted to the IPA within thirty (30) days of the Commission Bid Approval Date regardless of whether Construction Activities have been performed or will be performed in that delivery year. Starting with the second MES Compliance Plan, each MES Compliance Plan shall be combined with the MES Report as described in Section 6.4(c)(ii) due on July 15 each year.
- MES Compliance Plan and MES Report. By July 15 of each delivery year, Seller shall submit to the IPA a combined report for MES Compliance Plan and the MES Report in accordance with the IPA’s long-term renewable resources procurement plan as approved by the ICC in ICC Docket No. 25-0945. The submission shall include a backward-looking MES Report (for entities to demonstrate how they achieved MES compliance in the previous delivery year), as well as a forward-looking MES Compliance Plan (for entities to demonstrate how they will achieve MES compliance in the new delivery year). The MES Report portion shall include data on actual performance compared to the information previously submitted as well as any major differences from the previously submitted MES Compliance Plan for such delivery year. These differences could include information such as new and innovative ways to provide employment opportunities to low-income participants and residents within the Environmental Justice Communities. The MES Compliance Plan portion shall include: (a) a narrative description of how Seller will meet the Minimum Equity Standard and a statement of intent to comply with equity accountability standards for the applicable delivery year and to hire a diverse project workforce including Equity Eligible Persons and Equity Eligible Contractors; (b) projected number of workers and the demographic breakdown by race, gender, and participation in job training or workforce development programs, or other means of compliance with the standard for Equity Eligible Persons; (c) plans for the use of Equity Eligible Contractors, if applicable; (d) Seller classification (i.e., Minority-owned, Woman-owned, Disabled-owned, Veteran-owned, Small Business, etc.), if applicable; (e) communication plan for local outreach to increase the utilization of Equity Eligible Persons and Equity Eligible Contractors; and (f) status of any corrective actions or adjustments from the prior delivery year’s MES Compliance Plan.
- Mid-Year MES Confirmation. No later than December 1 of each delivery year, Seller shall provide to the IPA a statement confirming that Seller is on track to meet the Minimum Equity Standard and that there exist no impediments for Seller to meet the Minimum Equity Standard for such delivery year. If Seller is unable to provide such confirmation, Seller shall explain why it is unable to meet the Minimum Equity Standard for such delivery year. The Mid-Year MES Confirmation shall be submitted to IPA in accordance with procedures established by the IPA.
The Seller must submit the reports required by Section 6.4 Minimum Equity Standard of the Indexed REC Contract to the IPA separately for each such Project.
04-16-2026A Minimum Equity Standard of 14% will apply under the Indexed REC Contract to a Project selected through this RFP if the Date of First Operation (or the Hydropower Refurbishment Completion Date if the Project is a hydropower project that is newly Modernized or Retooled) is on or after December 15, 2022.
The remedies related to a failure to meet the percentage requirement of the Minimum Equity Standard (i.e., 14%) is described in Section 10.1.6 of the IPA’s 2026 long-term renewable resources procurement plan (the “Long-Term Plan”), which is pasted below for your convenience. Further, please also note that Section 1-75(c-30) of the IPA Act provides the following: “……If the Agency concludes the entity has not met or maintained its minimum equity standards required under the applicable subparagraphs under subsection (c-10), the Agency shall deny the entity’s ability to participate in procurement programs in subsection (c), including by withholding approved vendor or designee status.”
As set forth in Section 6.4(d) of the Indexed REC Contract, “no other remedies are contemplated under the Indexed REC Contract for Seller’s failure to comply with the Minimum Equity Standard requirements”. As such, failure to meet the percentage requirement of the Minimum Equity Standard is not an event of default leading to contract termination or forfeiture of the performance assurance under the Indexed REC Contract.
As noted above, and for your convenience, Section 10.1.6 of the 2026 Long-Term Plan provides that:
“If the IPA determines that an Approved Vendor, Designee, or Competitive Procurement Supplier has failed to comply with the applicable MES requirements, the entity will be notified and may face disciplinary action.
The Agency may impose consequences for violations by program participants, including, but not limited to the following:
- Notice of Potential Violation;
- Provision and implementation of a Corrective Action Plan;
- Suspension of the entity’s ability to submit project applications to IPA programs or to participate in competitive procurements until compliance is achieved; and
- For repeated violations – suspension of the entity’s ability to participate in IPA programs for an entire Program/delivery year or more or to participate in future competitive procurement events.
If an Approved Vendor or Designee in Illinois Shines fails to comply with any of the MES requirements, the entity will receive a Notice of Potential Violation (“NOPV”). If, after receiving the NOPV, the entity still does not meet the Agency’s requirements, the Agency will issue an official warning letter to the entity. If the entity does not come into compliance after receiving a warning letter, it will be issued a suspension letter.
If the Agency initially determines that a Competitive Procurement Supplier has failed to comply with the requisite MES, the Agency will notify the entity in writing. Following communication of this initial determination, the IPA may request any additional reports, information, and documentation that are reasonably necessary to determine compliance. If the requested materials are not received by the Agency within 21 days, the Agency may render a finding of noncompliance. Requests for an extension for more time to provide such additional information must be made prior any deadlines and will be considered on a case-by-case basis.
Suspensions of an Approved Vendor or Designee in Illinois Shines will be noted on the Program website’s lists of Approved Vendors and Designees, as well listed on the disciplinary actions report and in the Energy Workforce Equity Portal. Suspensions of Competitive Procurement Suppliers will be noted on the Procurement Administrator’s website, as well as the Energy Workforce Equity Portal.”
Please see Section 6.4 of the Indexed REC Contract as well as the FAQs page for additional information on the MES including requirements, compliance plans, and waiver requests.
04-16-2026Please see paragraph VI.2.19. of the RFP Rules. At the time of Commission approval of a procurement event, the names and contact information of winning Bidders, the average of the winning Bid prices, and the business address and nameplate capacity of the Project are made public. Additionally, as approved under the 2026 Long-Term Plan, the Annual Quantity of RECs for Projects selected and approved by the Commission will also be released as long as the confidentiality of individual winning Bid prices is maintained. The Public Utilities Act states that participants in the procurement process will maintain the confidentiality of all other supplier and bidding information.
04-16-202604-16-2026
Whether providing bid assurance collateral in the form cash or a letter of credit for a Company, the Bidder must follow all instructions provided by the Procurement Administrator for transmission of bid assurance collateral to each Company. Such instructions were provided to Bidders that submitted a Part 1 Proposal on Monday, May 4, 2026. Such instructions specify that the Bidder must provide cash by wire transfer and that the original executed Pre-Bid Letters of Credit must be in the form of Appendices 5, 6 and 7 to the RFP Rules if submitting the letter of credit via electronic means or in the form of Appendices 8, 9 and 10 to the RFP Rules if submitting the letter of credit to a physical address. The letter of credit may include only modifications to the Standard Pre-Bid Letter of Credit acceptable to that Company, applicable specifically to either the Electronic Version or Hardcopy Version, and posted to the procurement website.
04-16-2026Second, the annual quantity that you bid and win in the RFP will be the “RFP Awarded Annual Quantity” in each of the Indexed REC Contracts. The Annual Quantity in a contract will reflect the portion of the RFP Awarded Annual Quantity allocated to such contract. The Maximum Contract Quantity will be equal to the Annual Quantity indicated in such contract multiplied by 20.
04-16-2026Projects with winning Bids approved by the Commission will be assessed a Supplier Fee per REC that reflects the cost of conducting the procurement event less the total of the Bid Participation Fees. The exact amount of the Supplier Fee per REC will be announced no later than two (2) business days before the Bid Date. Payment of the Supplier Fees to the IPA by the Bidder or Seller will be due within seven (7) business days after Commission approval of the Bids. An estimate of the Supplier Fee per REC is provided in the webcast.
04-16-2026If a Seller has a Project with approved Bids, each Company prepares and sends a partially executed electronic copy of the Indexed REC Contract and related documents to the Seller. Each Company expects to provide such documents to Seller on the same day as the Commission approval, but no later than by 12 PM (noon) on the first business day after the Commission decision. The effective date of the Indexed REC Contract shall be the date of the Commission approval of the results of the procurement event. It is expected that the signatory named in the Contract Insert for each Company’s Indexed REC Contract will sign a copy of the partially executed Indexed REC Contract and related documents. If this individual is not available to sign the Indexed REC Contract and related documents, the Seller will advise each Company of this fact, will name another individual to sign the Indexed REC Contract and related documents, and will confirm that this individual is an officer, a director, or an individual otherwise authorized to undertake contracts (including the applicable supplier contract documents) and bind the Seller.
By 12 PM (noon) CPT (1 PM Eastern Prevailing Time) on the third business day after the Commission decision, the Seller executes the signature pages of the partially executed Indexed REC Contracts and related documents and sends such fully executed signature pages to each Company electronically. Creditworthiness requirements under the applicable Indexed REC Contract must be met within fifteen (15) business days after the Commission decision in accordance with the terms of the Indexed REC Contract. Upon execution of the Indexed REC Contracts and related documents in counterparts by both parties, such Indexed REC Contracts and related documents are fully executed.
The Procurement Administrator will provide instructions to each Bidder qualified pursuant to a successful Part 1 Proposal for executing and completing the Indexed REC Contract should the Bidder have winning Bids that are approved by the Commission. The Procurement Administrator will outline such instructions as part of the webcast to be held at or prior to the opening of the Part 1 Window.
04-16-2026The REC Monthly Price applicable to the Project with respect to a Vintage month shall be calculated as follows. The REC Monthly Price Hourly Component is the product of (a) the result obtained by subtracting the Strike Price from the Index Price of such hour and (b) the MWh actual generation of the Project for such hour. The REC Monthly Price for a Vintage month shall be calculated by dividing (a) the sum of all REC Monthly Price Hourly Components in such Vintage month by (b) the MWh actual generation of the Project for such Vintage month, and rounding to the nearest cent. The REC Monthly Price may be either positive or negative. Payment is made from Seller to Buyer if the REC Monthly Price is positive and payment is made from Buyer to Seller if the REC Monthly Price is negative.
Please review the Indexed REC Contract posted to the Final Materials page of the procurement website for additional information.
04-16-2026Section 1-75(c)(1)(D) of the Act states that, “Renewable energy credits shall be cost effective. For purposes of this subsection (c), “cost effective” means that the costs of procuring renewable energy resources do not cause the limit stated in subparagraph (E) of this paragraph (1) to be exceeded and, for renewable energy credits procured through a competitive procurement event, do not exceed benchmarks based on market prices for like products in the region. For purposes of this subsection (c), “like products” means contracts for renewable energy credits from the same or substantially similar technology, same or substantially similar vintage (new or existing), the same or substantially similar quantity, and the same or SB2408 Enrolled LRB102 11366 BMS 16699 b Public Act 102-0662 substantially similar contract length and structure. Benchmarks shall reflect development, financing, or related costs resulting from requirements imposed through other provisions of State law, including, but not limited to, requirements in subparagraphs (P) and (Q) of this paragraph (1) and the Renewable Energy Facilities Agricultural Impact Mitigation Act. Confidential benchmarks shall be developed by the procurement administrator, in consultation with the Commission staff, Agency staff, and the procurement monitor and shall be subject to Commission review and approval. If price benchmarks for like products in the region are not available, the procurement administrator shall establish price benchmarks based on publicly available data on regional technology costs and expected current and future regional energy prices. The benchmarks in this Section shall not be used to curtail or otherwise reduce contractual obligations entered into by or through the Agency prior to June 1, 2017 (the effective date of Public Act 99-906).”
Additional information regarding the benchmark development process is provided in an Invitation to Comment posted to the Draft Documents page on the procurement website. Stakeholder comments on the benchmark categories of inputs, assumptions, and data sources were due on Friday, April 10, 2026.
04-16-2026However, please note, each Project selected through this RFP with a Bid approved by the Commission must deliver at least one REC to each Company by December 31, 2030. Notwithstanding the foregoing, such deadline may be extended to May 31, 2033 if Seller meets an increased collateral requirement; and may be further extended as described in the Indexed REC Contract.
04-16-2026Yes, office staff related to the Project may be included in the Project Workforce for purposes of the Minimum Equity Standard (MES) requirements, provided they are located in Illinois.
As the MES of 14% is a contractual obligation, please rely on definition of “Project Workforce” in Section 1.96 of the Indexed REC Contract for purposes of determining the percentage of EEPs in the Project Workforce:
“‘Project Workforce’ means employees, contractors and their employees, and subcontractors and their employees whose job duties are directly required by or substantially related to the development, construction, and operation of the Project that is participating in the IPA-administered programs and procurements under Section 1-75(c) of the IPA Act. This shall include both project installation workforce and workforce in administrative, sales, marketing, and technical roles where those workers’ duties are directly related to the Project. For workforce in administrative, sales, marketing and technical roles, this shall apply only if those workers are located in Illinois. For purposes of this definition, “directly required by or substantially related to” shall be construed to be any direct employee of Seller, or any contractor and its employees whose contract exceeds 5% of the REC Contract Value. Employees of contractors below that threshold may be counted toward the MES on a voluntary basis, but then all employees of all contractors below the 5% of REC Contract Value threshold must be included.”
04-16-2026If you bid and win in the RFP, the RECs from your winning Project will be allocated by the Procurement Administrator to the Companies in pre-specified proportions (26.44% to AIC, 73.34% to ComEd, and 0.22% to MEC). As such, you will sign three contracts, one with each of AIC, ComEd, and MEC. Each Indexed REC Contract is administered separately and independently by each of Companies, as such the Performance Assurance is determined for each of AIC, ComEd, and MEC independently.
The amount of the Performance Assurance is defined in Section 7.1 of the Indexed REC Contract. “The amount of such Seller’s Performance Assurance shall be equal to the positive difference, if any, between: (a) the Collateral Requirement (or Increased Collateral Requirement, if applicable); and (b) the Collateral Threshold, as estimated by Buyer (“Performance Assurance Amount”).”
For an entity that is not eligible for unsecured credit under the Indexed REC Contract, Collateral Requirement means, (a) with respect to a Utility-Scale Wind Project or a Hydropower Project, an amount equal to four dollars ($4) times the Annual Quantity and which shall be reduced for the last Delivery Year, if applicable, to reflect an amount equal to the product of the Delivery Year Requirement for the last Delivery Year and four dollars ($4); provided that if the Collateral Requirement is calculated to be less than $20,000, then the Collateral Requirement shall be $20,000; and means, (b) with respect to a Utility-Scale Solar Project or a Brownfield Site Photovoltaic Project, an amount equal to ten dollars ($10) times the Annual Quantity and which shall be reduced for the last Delivery Year, if applicable, to reflect an amount equal to the product of the Delivery Year Requirement for the last Delivery Year and ten dollars ($10); provided that if the Collateral Requirement is calculated to be less than $20,000, then the Collateral Requirement shall be $20,000.
A Seller with a Project with an approved Bid must meet the creditworthiness requirements under the Indexed REC Contract within fifteen (15) business days of the Illinois Commerce Commission decision on the results of the procurement event.
04-16-2026For Contracts executed under this Summer 2026 Indexed REC RFP, the minimum percentage indicated in the Product Order for the Minimum Equity Standard shall not change during the term of the Indexed REC Contract.
Please review paragraph IV.3.1 of the RFP Rules and Section 6.4 of the Indexed REC Contract for additional information.
04-16-2026No. The arrangement proposed in your example is prohibited under the Indexed REC Contract. In order for the REC Monthly Price Hourly Component to be calculated under the Indexed REC Contract, the Project must allow for its MWh production (as opposed to energy exported from the storage facility) to be measured for each hour.
04-16-2026Please note, the Officer of the Seller must certify that the Project has or will have a single revenue quality meter that satisfies the requirements of the applicable regional transmission organization, transmission provider, or distribution company and that measures or will measure its generation output. Also, if one of the documents listed in Paragraph IV.6.2 of the RFP Rules to demonstrate adequate project maturity is not available, the Bidder must provide the required information in Paragraph IV.6.3 including demonstrating site control for a portion of the Project site.
04-16-2026In order to bid a remainder (or another portion) of the RECs from the Project, the Bidder is required to confirm that (1) the Project in the procurement event represents an additional portion of RECs from the renewable energy facility; (2) the Project in the procurement event will have a revenue quality meter separate from the meter associated with the RECs selected and approved in a prior procurement event; and (3) the Project in the procurement event will have its own account within PJM EIS GATS or M-RETS for purposes of tracking only the additional portion of RECs associated with the Project.
04-16-202604-16-2026
- Bid Assurance (Pre-Bid) Collateral
All Bidders are required to submit Bid Assurance Collateral regardless of whether the Seller or Seller’s Guarantor is rated. Bid Assurance Collateral must be posted separately with each Company in the form of cash or a Pre-Bid Letter of Credit and the amount required is based on the Project size. Please refer to paragraph V.2.1 of the RFP Rules for the specific calculations of Bid Assurance Collateral required for each Company. Please note that if you are using a Pre-Bid Letter of Credit, there are separate standard forms for Bid Assurance Collateral (Pre-Bid) and Performance Assurance Collateral (Post-Bid). The Standard Pre-Bid Letters of Credit are posted as appendices to the RFP Rules on the Final Materials page: https://www.ipa-energyrfp.com/indexed-renewables/final-materials/
- Performance Assurance (Post-Bid) Collateral
If a Bid for a Project is selected and approved by the Illinois Commerce Commission, the RECs from the Project will be allocated by the Procurement Administrator to the Companies in pre-specified proportions (27.09% to AIC, 72.67% to ComEd, and 0.24% to MEC). Therefore, you will sign three contracts, one with each of AIC, ComEd and MEC.
Each Indexed REC Contract is administered separately and independently by each of Companies (each is the Buyer under each such Indexed REC Contract). The Collateral Threshold amount determined in accordance with Table A in Section 7.1 of the Indexed REC Contract, and the Performance Assurance Amount, applies to each of AIC, ComEd, and MEC independently. The Collateral Threshold amount is dependent on the credit ratings available for the Seller or the Seller’s Guarantor, if applicable. If the Seller is relying on a Guarantor and Seller’s Guarantor has provided a Guaranty, the Collateral Threshold shall be the lesser of the Collateral Threshold as determined by (i) the table in Section 7.1 or (ii) the amount of such Guaranty. If the Seller or Seller’s Guarantor is a party to one or more additional Indexed REC Contracts with a Buyer, then the Seller or Seller’s Guarantor will be granted a single Collateral Threshold to be applied in aggregate to all such Indexed REC Contracts entered into with such Buyer.
The amount of a Seller’s Performance Assurance is equal to the positive difference, if any, between: (a) the Collateral Requirement (or Increased Collateral Requirement, if applicable); and (b) the Collateral Threshold, rounded up to the nearest $10,000, as estimated by Buyer (“Performance Assurance Amount”). Performance Assurance may be posted in the form of cash or a Post-Bid Letter of Credit. There are two options for the Post-Bid Letter of Credit posted with the final contract documents to the Final Materials page: https://www.ipa-energyrfp.com/indexed-renewables/final-materials/
For example, for a utility-scale solar project, if the Annual Quantity allocated to the Indexed REC Contract with ComEd is 300,000 RECs, and the Seller’s Guarantor is investment grade and has provided a Guaranty in an amount equal to the Collateral Threshold of $2,500,000, then the required Performance Assurance Amount to be posted with ComEd is $500,000 ($10 x 300,000 – $2,500,000). A similar calculation would be performed to calculate the required Performance Assurance Amount to be posted separately with each of AIC and MEC. This example assumes that the Seller is party to only one Indexed REC Contract with each utility and the Seller is not posting the Increased Collateral Requirement.
04-16-202604-16-2026
Section 1-75(c)(1)(I) of the IPA Act permits qualifying renewable energy credits may be sourced from facilities in adjacent states—but only if these facilities can meet public interest criteria spelled out in the law. The public interest criteria that the Agency considers include:
- Minimizing sulfur dioxide (SO2), nitrogen oxides (NOx), particulate matter (PM), and other pollution that adversely affects public health in this State
- Increasing fuel and resource diversity in this State
- Enhancing the reliability and resiliency of the electricity distribution system in this State
- Meeting goals to limit carbon dioxide emissions under federal or state law
- Contributing to a cleaner and healthier environment for the citizens of this State
The 2026 Long-Term Plan includes specific details about the methodology for evaluating each criterion.
04-16-2026If the Project is located in a state adjacent to Illinois and has been pre-approved by the Illinois Power Agency (“IPA”) to be eligible for Illinois RPS compliance based on public interest criteria, the Bidder must provide evidence of this determination with the Part 1 Proposal by upload to the online form or by email to Illinois-RFP@nera.com. The Part 1 Proposal, including this evidence and all other required supporting documentation, is due by 12PM (noon) CPT on Thursday, April 30, 2026.
04-16-2026“A Bidder presenting Proposals for multiple Projects and that elects to provide bid assurance collateral in the form of a letter of credit for a Company may present a single Pre-Bid Letter of Credit to that Company for all Projects presented by the Bidder provided that: (i) the Bidder and all Sellers are properly identified in the Pre-Bid Letter of Credit; and (ii) the entity or entities named in Paragraph 2 of the letter of credit consist of the Bidder, and/or one or more of the Sellers, and/or another entity identified in the Part 1 Proposal and associated with the Projects. Notwithstanding the provision of this paragraph, a Bidder consisting of a group of Sellers may, at its option, provide more than one letter of credit (for example, providing a separate letter of credit for each Project) instead of providing a single letter of credit for all Projects presented by the Bidder.”
04-14-2026The Indexed REC Contract does not allow for a ramp up of the quantity of RECs to be delivered at a point during the delivery term.
There is an option for the Seller to indicate a percent of the project’s output to commit to the Buyer under the Indexed REC Contract so as to allow for a third party off-taker to procure a portion of the project’s output that is not committed to the Buyer under the applicable the Indexed REC Contract. Please review Section 2.3(b) of the Indexed REC Contract for information regarding the Project Committed Percentage and the Standing Order.
04-14-2026The minimum quantity of each Project presented by a Bidder may not exceed the Target for the Category associated with that Project. The full quantity may exceed the Target of the Category associated with the Project. However, if the Bidder selects a full quantity that exceeds the Target, the Bidder will be required to acknowledge that the Project could only be selected at a quantity above the Target if: (i) the evaluation proceeds to the Reallocation Stage; and (ii) the Category associated with the Project is Oversubscribed.
04-13-2026Please see Table 5-5 in Section 5.6 of the 2026 IPA Long-Term Plan, which lists the proposed procurement targets for upcoming competitive procurement events. Please note that these targets are not final and may be adjusted as described in Section 5.6. The Fall 2026 Indexed REC RFP targets will not be finalized until after the conclusion of the Summer 2026 Indexed REC RFP.
04-13-2026The Procurement Administrator cannot provide any guidance on how to select the Index Hub. The bidder provides either MISO-IL Hub or PJM-NIHUB as the Index Hub for their Project in the online Part 2 Form. The Seller may elect either the MISO-IL Hub or PJM-NIHUB as the hub for the Index Price for the Project, regardless of whether the Project is or will be interconnected to MISO or PJM.
04-08-2026The “Seller” is an entity that bids to deliver RECs from a Project under the terms of the Indexed REC Contract and that will be the signatory to the Indexed REC Contract if the Bid for the Project is selected through this RFP and the Bid is approved by the Commission.
The “Bidder” is the entity submitting the Proposal. The Bidder may present a Proposal for one (1) or multiple Projects with the same or different Sellers. If an entity has a role in the development of multiple Projects, this entity must serve as the Bidder and present the Proposals for all such Projects. If several entities each have a role in the development of the same multiple Projects, one (1) of these entities must be selected to present the Proposals for all such Projects and serve as the Bidder.
04-08-2026The certifications related to confidentiality are provided in the P2 Confidentiality Certifications Insert (#P2-7) posted to the Final Materials page of the RFP website and also listed in paragraph V.5.2 of the RFP Rules.
Additional rules may apply to a Joint Venture Project or other Projects in specific circumstances. Please advise the Procurement Administrator as soon as possible if the Seller for your Project is the product of a Joint Venture or similar agreement.
04-08-2026See FAQ-Indexed REC-5 for more information on Contributors.
04-08-2026The Contributors include individuals already named in the Part 1 Proposal, including the Officer of the Seller and the Representatives (and all Signatories for a Joint Venture) by default. Also, individuals employed by the Seller or by the Bidder or by a Partner of a Joint Venture Project and concerned with the Project are Contributors by default. These individuals do not need to be but may be named again in the Contributor Insert (#P1-3). If there are no other Contributors other than those already named in the Part 1 Proposal then the Bidder will indicate this fact in the seventh item of Section 1 and the Contributor Insert (#P1-3) is not required.
04-08-2026Entities already named in the Part 1 Proposal, namely the Bidder, the Seller (and all Partners for a Joint Venture), are already included on the Project Team by default. These entities already named in the Part 1 Proposal do not need to be named again in the Project Team Insert (#P1-2). If there are no other entities involved in the development of the Project other than those already named in the Part 1 Proposal then the Bidder will indicate this fact in the sixth item of Section 1 and the Project Team Insert (#P1-2) is not required.
04-08-2026Attached is a sample of a confidentiality agreement and a confidentiality process that Bidders and Sellers can use, at their option, to ensure that the confidentiality of the Proposal is properly maintained in accordance with the Indexed REC RFP. It is not a requirement of the Proposal to provide evidence of use of this sample or process. This document is provided for the convenience of Bidders and Sellers.
04-06-2026Whether providing bid assurance collateral in the form cash or a letter of credit for a Company, the Bidder must follow all instructions provided by the Procurement Administrator for transmission of bid assurance collateral to each Company. Such instructions are provided after submission by the Bidder of a Part 1 Proposal and by the date of the Part 1 Notification. Such instructions specify that the Bidder must provide cash by wire transfer.
04-03-2026Please refer to Section 5.5.5 of the Illinois Power Agency (“IPA”)’s filed 2026 Long-Term Renewable Resources Procurement Plan, which provides rationale for the exclusion of repowered wind projects from the IPA’s competitive procurement events:
“P.A. 103-1066 added “repowered wind projects” to the list of project types that qualify to produce RECs to meet Illinois RPS goals. Under Section 1-75(c)(1)(C)(iii) of the IPA Act, a “repowered wind project” refers to “utility-scale wind projects featuring the removal, replacement, or expansion of turbines at an existing project site.” That definition may be further refined through Long-Term Plan development.
As support for projects that have already been financed and constructed would not be the most impactful use of RPS funds, Section 1-75(c)(1)(C)(iii) clarifies that REC contract awards made to repowered wind projects “shall only cover the incremental increase in facility electricity production resultant from repowering.” As with brownfield site photovoltaic projects, Section 1-75(c)(1)(C)(i) clarifies that the Agency “shall consider and may propose other approaches in addition to competitive procurements to procure renewable energy credits from repowered wind projects.”
At this time, the IPA is unaware of any existing RPS-compliant utility-scale wind projects planning to repower, but suspects that dedicated support for repowering may become an issue across the next planning cycle. Nevertheless, the draft 2026 Plan solicited stakeholder feedback as to 1) whether the IPA should allow for repowered wind project participation, 2) if so, whether repowered wind projects should compete on the basis of price against new utility-scale wind projects, and 3) whether alternative procurement approaches for repowered wind projects other than the Agency’s Indexed REC procurement process should be considered. In the draft Plan, the Agency noted that if commenters demonstrated serious interest in RPS support for repowering wind projects through comments on this 2026 Plan, the Agency would reconsider its approach in this filed Plan; however, the Agency did not receive public comments related to repowered wind. Consequently, the IPA is not proposing procurement events or procurement event eligibility for repowered wind projects as part of this Plan.”
04-03-2026